The management holds your renovation deposit until it inspects at the end of the job. What it looks at, what the by-laws say, and how to keep deductions off the table.
📍 We serve KL, Selangor & Putrajaya.

A condo renovation deposit is money the management holds while you renovate, as security that the works keep to the building's by-laws and do not damage common property; you usually get it back after the management inspects the unit and the common areas at the end. The refund depends on that inspection, so prepare for it like a handover: clear the debris, fix any damage outside your door, and ask for the result in writing. To have the works checked before you call the management, see renovation inspection.
Every strata building in Malaysia runs on the standard by-laws in the Third Schedule to the Strata Management (Maintenance and Management) Regulations 2015. By-law 27(1) says an owner may not carry out renovation works without first getting the management's written approval and, where needed, the local authority's. By-law 27(2) lets the management, in giving that approval, require the owner to place an amount with it as a deposit for compliance with the by-laws, and any additional by-laws, relating to the works. It may also require the works to be finished within a certain time.
Read that carefully, because it shapes the refund. The deposit is not a fee and it is not held against the quality of the work inside your unit. It is held against breaking the renovation rules and damaging what belongs to everyone. Those by-laws apply whether the building is run by the developer, a joint management body or a management corporation; by-law 2 reads “management corporation” as whichever of them is in charge.
Your building may add its own renovation rules on top. A JMB under section 32(3) and an MC under section 70(2) of the Strata Management Act 2013 can make additional by-laws by special resolution. Ask the management office for a copy of the additional by-laws and the renovation form you signed; the refund conditions are usually set out there.
Buildings differ, but the final check tends to follow the by-laws. This is what is commonly looked at, and what to do about each before you ask for the inspection:
| Area | What the management looks for | What to do first |
|---|---|---|
| Lift and lift lobby | Scratches, dents or stains from moving materials | Compare with the condition recorded before works began |
| Corridor outside your unit | Cement stains, chipped floor tiles, marks on walls and doors | Clean and make good anything your contractor caused |
| Refuse chamber and bin area | Renovation debris left in common bins | Have the contractor clear it out of the building |
| Facade, windows and balcony | Changes to the outside look that were not approved | Check that any grille, window or awning matches the approval |
| Common services | Damage to shared pipes, risers or ducts | Ask the plumber to confirm nothing common was touched |
| Approved scope | Works beyond what the form approved | Have the approved scope to hand during the visit |
By-law 27(4) confines renovation works to the boundaries of the parcel, with no works on any part of the common property. By-law 27(7) makes the owner fully responsible for any defect or damage to common property caused by the works, to be made good to the management's satisfaction. By-law 27(8) adds a duty to take precautions against damaging concealed wirings, cables, pipes and ducts.
In practice this means two separate questions at the end of your job. The management asks whether the building is as it was. You should be asking whether your own unit is as you paid for. A deposit can come back in full on a job with leaking showers and hollow tiles, because those are your contractor's problem, not the building's. Do not treat a refund as a quality pass on the work.
The strongest position at the final inspection is set on day one. Before the first worker arrives:
If the condition of neighbouring units is a concern too, a pre-renovation condition survey records them before the noisy work begins.
Most deductions come from small, avoidable things. By-law 27(5) says renovation waste must not be left in the refuse chamber or any part of the common property and has to be removed from the building, unless the building has an approved facility for it. By-law 29(2) bars changes to the exterior appearance of the unit or the facade without the management's written approval.
So ask the contractor to bag and remove debris as it is made, to mix cement inside the unit on a sheet rather than in the corridor, and to keep within the approved scope. Wall hacking deserves its own care: the guide to hacking walls in a renovation explains why structural walls are off limits. A crack, sagging beam or removed wall that may affect the structure needs a professional engineer's assessment.
One by-law reaches inside your unit. By-law 27(9) says that if you change the floor finishes in a wet area, you must replace the existing damp proof membrane with a new one, continuing upwards at any wall junction for at least 150 mm high, and that changing wet-area wall tiles means replacing the affected part of the membrane at the wall-floor junction.
A leak into the unit below is the kind of damage that can follow you long after the deposit is settled. Most management inspections will not see the membrane at all, because it is under the tiles by then. If your job retiles a bathroom or kitchen, check the membrane yourself before tiling starts, or have it checked, and keep a dated photo of it running up the wall corners.
Do the management's inspection yourself first, the day before you ask for theirs:
Ask for the final inspection by email or letter, not just at the counter, and keep the date. In the same message, ask to be present at the inspection, ask for the result in writing, and ask how long the refund takes under the building's rules. If the management needs a completion notice from your contractor or a form signed by you, send it with the request.
Go to the inspection if you can. Points raised face to face can often be settled on the spot with a cloth or a touch-up, before they become a deduction on paper. Afterwards, file the written result with your other job papers; the guide to renovation handover documents lists what else to keep.
| Reason given | What to ask for in writing | Points to consider |
|---|---|---|
| Damage to the lift or lobby | The finding, a picture of it and the repair quotation | Compare with the before-works condition record |
| Debris in common areas | When it was found and what it was | Whether it can be traced to your works at all |
| Works beyond the approval | Which approved item was exceeded | Whether the item is inside the unit only, or affects common property or the facade |
| Works finished late | The deadline in the approval or additional by-laws | Whether the time limit was written down |
| No reason, or no reply | The by-law or house rule relied on and the date of the decision | Escalate to the committee, then consider the routes below |
Keep every exchange polite and in writing. Ask the management to name the by-law or additional by-law it relies on and to show the damage; a deduction tied to a specific finding is far easier to agree or dispute than a general one.
Start with the management office, then the committee of the JMB or MC. If that fails, the Strata Management Tribunal under section 105 of the Strata Management Act 2013 hears the claims listed in Part 1 of its Fourth Schedule. These include a dispute about how a management body has exercised or failed to exercise a function, duty or power under the Act or its regulations, and a claim to compel it to supply information or documents. Whether your deposit dispute fits, and what the Tribunal may order, depends on your facts; check with the Tribunal or a lawyer first. The guide to the Strata Management Tribunal explains how claims are filed.
Before you book the management's inspection, ClickBina can look over the job for you. What we offer is a third-party inspection of your contractor's work; if you want, we can also quote the repairs. We walk the unit against your quotation, drawings and materials list, and the common areas along the materials route, and we go through what we found with you so you can settle it with the contractor first.
This page is general guidance, not legal advice. Your building's additional by-laws and the approval you signed set the actual refund conditions.