Opening a shop, cafe, restaurant, clinic or salon? ClickBina designs and builds the interior — shopfront, counters, ceilings, lighting, flooring and joinery — planned backwards from your opening date and the mall or landlord’s fit-out rules.

A shop or restaurant fit-out runs on a fixed date: the mall’s fit-out period, the end of a rent-free month, or a launch you have already announced. We plan the works backwards from that date, design the space around how customers move through it, and build the interior: shopfront, counters and display, ceilings and lighting, flooring, wall finishes and joinery.
Below: what a retail and F&B fit-out costs per sq ft in 2026, the project types we take on, how long each takes, the approvals a tenant needs, and what to send us for a quote. For offices, see our office fit-out page.
Fit-out is priced per square foot of the lot. These are the indicative 2026 Klang Valley ranges from our cost guides; your figure depends on the lot, the concept and how much mechanical and electrical work the space needs. Small-format F&B such as a kiosk or bubble-tea counter is covered in coffee kiosk & bubble-tea shop fit-out.
| Type of fit-out | Indicative cost per sq ft (2026) | What sits in that band |
|---|---|---|
| Retail shop — standard | RM80 – RM150 | Shelving, counter, basic lighting, flooring, paint, simple shopfront |
| Retail — mid concept store | RM150 – RM250 | Custom joinery, feature lighting, branded shopfront, display zones |
| Retail — high-spec / flagship | RM250 – RM400+ | Premium finishes, heavy M&E, bespoke fixtures |
| Cafe — kiosk to design-led | RM150 – RM300+ | Espresso bar, light kitchen, designed seating, feature lighting |
| Restaurant — quick-service to fine dining | RM150 – RM400+ | Commercial kitchen with exhaust and grease trap, dining, bar |
| Clinic — GP to dental | RM150 – RM300+ | Reception, consultation and treatment rooms; dental adds chairs, suction and an X-ray room |
| Salon — budget to concept | RM120 – RM280+ | Styling stations, wash basins, mirrors, lighting and branding |
In practice most independent Klang Valley retailers land around RM100–RM200 per sq ft once the shopfront, lighting and a decent counter are in; most cafes around RM200–RM280; and a typical KL casual-dining restaurant around RM200–RM320 once the kitchen, exhaust and dining are properly built. Most independent salons land around RM150–RM230 per sq ft. A fashion store’s fitting rooms and display are covered in boutique fashion store fit-out.
F&B costs more than retail because of the commercial kitchen: exhaust, grease traps, heavy-duty plumbing and gas, plus Bomba and health-authority compliance. Our restaurant fit-out cost guide notes that starting a cafe or restaurant in Malaysia can reach RM300,000–RM500,000 all-in, with renovation and equipment the biggest slices. Kitchen exhaust, gas and fire-suppression systems are specialist works: at the site visit we will set out which parts of the kitchen fit-out sit in our scope and which need a specialist, so your budget has no gaps. The food premises layout checklist lists what the council’s health inspectors look for. For fitness tenants, floor load and noise shape the budget — see the gym fit-out cost guide.
WhatsApp us your lot size and the mall or street and we will tell you which band your concept is likely to fall in.
Restaurants take longest because of the kitchen build and inspections; retail is the lightest. Indicative durations from our cost guides:
| Project | Design & approvals | On site | End to end |
|---|---|---|---|
| Retail shop (small to medium) | 2 – 3 weeks | 4 – 8 weeks | — |
| Cafe | 2 – 3 weeks | 5 – 8 weeks | 7 – 11 weeks |
| Restaurant | 3 – 4 weeks | 6 – 10 weeks | 9 – 14 weeks |
| Salon | 2 – 3 weeks | 4 – 7 weeks | 6 – 10 weeks |
| Clinic | Several weeks (incl. KKM) | 6 – 10 weeks | About 3 – 4 months |
On top of this, authority approval often takes about 2–6 weeks before site works can fully proceed. Starting design and submission late is the most common cause of a missed opening date.
Approvals are the tenant’s to obtain (or the owner’s, if you own the lot). What applies depends on your trade and how much the fit-out touches fire safety, layout and services. The usual set:
Our commercial renovation permit guide puts the authority submission (drawings by a registered professional, plus fees) at about RM8,000–RM25,000 depending on scope, and an unlicensed sign risks fines of roughly RM250 to RM5,000. A fit-out contractor typically supplies the layout drawings, finishes schedule and method statements; agree early who prepares and submits each application.
In a managed mall, the centre’s fit-out manual, approved-contractor list and management layer sit on top of the statutory approvals, and the mall often coordinates parts of the Bomba and base-service process. Expect tighter working hours, hoarding rules and a fit-out deposit that is refunded only after the mall inspects the reinstated area. In a standalone shoplot you deal directly with the council and Bomba yourself: more freedom over hours and layout, but more responsibility. Either way, the statutory approvals still apply. Read the fit-out manual or the tenancy agreement before you price the job, because its rules change both the cost and the programme.
Send these on WhatsApp and we reply within the hour.
Shopfront to back-of-house, planned to your opening date.
Customer flow, seating, counters and back-of-house planned around your concept and lot.
Storefront, display walls, shelving and the lighting that pulls people in.
Service counters, bar fronts, cabinets and bespoke fixtures, built to your layout.
Plaster and feature ceilings, track and feature lighting, and the electrical points your layout needs.
Tiles, vinyl, epoxy, wall panels, painting and the details customers notice.
A defects walk before opening, and reinstatement when a tenancy ends.
The programme is built backwards from your launch and the mall’s fit-out period.
A flat price for the agreed scope, with specialist and mall-nominated items listed separately.
WhatsApp us your lot details and we reply within the hour.
WhatsApp us your job details — we reply within the hour with a free quote.
💬 Get Your Free QuoteFree guides for shop, cafe and restaurant tenants:
Fill in a few details and it opens WhatsApp with your enquiry ready to send. We reply within the hour.
No spam — your details go straight to our team on WhatsApp.
WhatsApp us your requirements — we reply within the hour.