The lowest total is rarely the cheapest job. Here is how to put fit-out quotes on the same footing.

To compare fit-out quotations fairly, give every contractor the same tender package (drawings, finishes schedule and a bill of quantities), then level the returned prices line by line: add back anything one bidder left out, check quantities and specifications match, separate provisional and prime-cost sums, and compare preliminaries, exclusions, programme and payment terms before you compare totals. ClickBina's guides make the same point for any renovation: two quotes that look alike are usually two different scopes, and the cheapest total is often the one that leaves the most out.
A fit-out quotation total hides more than it shows. One contractor includes the aircon, another prices it as a provisional sum, a third leaves it out and writes 'by owner' in the small print. One allows for night works in a mall, another assumes day work. By the time the gaps are filled, the cheapest quote is often no longer the cheapest.
ClickBina's guide to reading a renovation quote puts it plainly: the honest comparison is item by item, not total against total, because two quotes with similar-looking prices are usually two different scopes. On a commercial fit-out, with more trades and more approvals, that gap is wider.
You can only compare like with like if every bidder prices the same thing. ClickBina's commercial fit-out process guide lists the basics: same drawings, same finishes, same exclusions. A good tender package includes:
Ask every bidder to price the package as issued, and to list any alternatives separately rather than quietly changing the specification.
A bill of quantities (BQ) breaks the work into numbered items, each with a description, a quantity, a unit and a rate, so that quantity times rate gives the amount for that line. ClickBina's guide to protecting a renovation budget explains why it matters: the scope is explicit, three quotes with identical items become directly comparable, variation orders can be priced against the agreed rates, and a low lump sum that hides missing items is exposed.
| BQ column | What it tells you | What to check |
|---|---|---|
| Item number and description | Exactly what is being priced | Same wording and specification across bidders |
| Quantity and unit | How much of it | Quantities match the drawings; units are the same (per point, per metre, per sq ft, lump sum) |
| Rate | The price per unit | Unusually low or high rates against the other bidders |
| Amount | Quantity times rate | Arithmetic is right; no amount without a quantity and rate |
| Provisional sum (PS) | An allowance for work not yet defined | Same allowances used by every bidder |
| Prime cost (PC) sum | An allowance for an item still to be chosen, such as a fitting | Same PC values, and how the markup on them is handled |
Preliminaries cover what the contractor needs to run the job rather than the work itself: site supervision, protection of the common areas, hoarding in a mall, debris disposal, insurance, temporary power and water, cleaning, and the paperwork for the building management. Some bidders price them in full, some spread them across the trade rates, and some leave them out. Put the preliminaries side by side as their own block before comparing anything else.
Levelling means adjusting each quote so they all price the same scope. Build a simple sheet with the BQ items down the side and one column per bidder:
| Line on the sheet | Bidder A | Bidder B | Bidder C |
|---|---|---|---|
| Partitions and ceilings | Priced | Priced | Priced |
| Aircon | Priced | Provisional sum only | Excluded: add allowance |
| Protection and disposal | Priced | In preliminaries | Excluded: add allowance |
| Night-works surcharge | Included | Not mentioned: ask | Priced separately |
| Approvals and submission | By owner | By owner | Included |
The table is the kind of pattern a levelling sheet shows. The cheapest raw total is often the bidder with the most 'excluded' and 'not mentioned' lines.
Every quotation has a list of exclusions, assumptions and qualifications, usually at the end. ClickBina's fit-out process guide names the common gaps: approvals, professional fees, landlord deposits, equipment and signage. Also look for:
Two quotes at the same levelled price are not equal if one opens your shop weeks later. Compare the programme, the payment schedule and how changes will be priced. A contractor who prices variation orders from the BQ rates gives you a benchmark for every change; ClickBina's variation order guide explains why that matters once work starts. The contract terms themselves, such as retention and the defects period, are a separate read.
WhatsApp us your job details for a quote: the premises, the drawings or BQ you have issued, and the target opening date. ClickBina is an experienced KL & Selangor contractor for whole-house refurbishment and trade coordination, and can price against your package as issued, with any alternatives listed separately. We reply within the hour, and the price we agree is a flat price with no hidden charges. A site visit is RM150, waived if you go ahead.
About this page: it describes a levelling method and quotes no prices for fit-out work, because a fair comparison depends entirely on the scope you issue. The worked table shows patterns, not real bids.