How to Compare Fit-Out Quotations & a BQ
🏠 Renovation🏢 Office Fit-Out🛍 Shop Fit-Out💦 Waterproofing❄ Aircon⚡ Electrical & Plumbing🔨 Carpentry🧹 Deep CleaningGuidesDesign IdeasToolsAbout🔍 SearchFree Quote
📋 Commercial Fit-Out

How to Compare Fit-Out Quotations
Reading and Levelling a Bill of Quantities (2026)

The lowest total is rarely the cheapest job. Here is how to put fit-out quotes on the same footing.

Tablet showing a colour-coded comparison sheet on gypsum boards inside a shop unit mid fit-out at night

To compare fit-out quotations fairly, give every contractor the same tender package (drawings, finishes schedule and a bill of quantities), then level the returned prices line by line: add back anything one bidder left out, check quantities and specifications match, separate provisional and prime-cost sums, and compare preliminaries, exclusions, programme and payment terms before you compare totals. ClickBina's guides make the same point for any renovation: two quotes that look alike are usually two different scopes, and the cheapest total is often the one that leaves the most out.

Why the lowest total is the wrong starting point

A fit-out quotation total hides more than it shows. One contractor includes the aircon, another prices it as a provisional sum, a third leaves it out and writes 'by owner' in the small print. One allows for night works in a mall, another assumes day work. By the time the gaps are filled, the cheapest quote is often no longer the cheapest.

ClickBina's guide to reading a renovation quote puts it plainly: the honest comparison is item by item, not total against total, because two quotes with similar-looking prices are usually two different scopes. On a commercial fit-out, with more trades and more approvals, that gap is wider.

Send one tender package to everyone

You can only compare like with like if every bidder prices the same thing. ClickBina's commercial fit-out process guide lists the basics: same drawings, same finishes, same exclusions. A good tender package includes:

  • The layout and any design drawings, with the revision date.
  • A finishes and fittings schedule: what goes where, with brand or grade where it matters.
  • A bill of quantities, or at least a pricing schedule with the same line items for everyone.
  • The landlord's or mall's fit-out rules: approved contractors, working hours, deposits, night works.
  • What you are supplying yourself, such as equipment, furniture or signage.
  • The target opening date and any fixed dates, such as the handover from the landlord.

Ask every bidder to price the package as issued, and to list any alternatives separately rather than quietly changing the specification.

What a bill of quantities is

A bill of quantities (BQ) breaks the work into numbered items, each with a description, a quantity, a unit and a rate, so that quantity times rate gives the amount for that line. ClickBina's guide to protecting a renovation budget explains why it matters: the scope is explicit, three quotes with identical items become directly comparable, variation orders can be priced against the agreed rates, and a low lump sum that hides missing items is exposed.

BQ columnWhat it tells youWhat to check
Item number and descriptionExactly what is being pricedSame wording and specification across bidders
Quantity and unitHow much of itQuantities match the drawings; units are the same (per point, per metre, per sq ft, lump sum)
RateThe price per unitUnusually low or high rates against the other bidders
AmountQuantity times rateArithmetic is right; no amount without a quantity and rate
Provisional sum (PS)An allowance for work not yet definedSame allowances used by every bidder
Prime cost (PC) sumAn allowance for an item still to be chosen, such as a fittingSame PC values, and how the markup on them is handled

Preliminaries: the costs outside the trades

Preliminaries cover what the contractor needs to run the job rather than the work itself: site supervision, protection of the common areas, hoarding in a mall, debris disposal, insurance, temporary power and water, cleaning, and the paperwork for the building management. Some bidders price them in full, some spread them across the trade rates, and some leave them out. Put the preliminaries side by side as their own block before comparing anything else.

Levelling the quotes: a worked method

Levelling means adjusting each quote so they all price the same scope. Build a simple sheet with the BQ items down the side and one column per bidder:

  1. Enter each bidder's amount against the matching item.
  2. Where a bidder left an item out, mark it and add an allowance using the other bidders' rates for that item.
  3. Where quantities differ from the drawings, correct them and recalculate using that bidder's own rate.
  4. Where a specification was changed, note the difference and price it back to the tender specification.
  5. Replace every bidder's provisional and prime-cost sums with the same allowances.
  6. Add the preliminaries and any items the bidder lists as extra, such as night-work surcharges.
  7. Only now compare the levelled totals, alongside the programme and the payment terms.
Line on the sheetBidder ABidder BBidder C
Partitions and ceilingsPricedPricedPriced
AirconPricedProvisional sum onlyExcluded: add allowance
Protection and disposalPricedIn preliminariesExcluded: add allowance
Night-works surchargeIncludedNot mentioned: askPriced separately
Approvals and submissionBy ownerBy ownerIncluded

The table is the kind of pattern a levelling sheet shows. The cheapest raw total is often the bidder with the most 'excluded' and 'not mentioned' lines.

Exclusions and qualifications to read line by line

Every quotation has a list of exclusions, assumptions and qualifications, usually at the end. ClickBina's fit-out process guide names the common gaps: approvals, professional fees, landlord deposits, equipment and signage. Also look for:

  • Authority submissions and fees, and who deals with the fire-safety side; ClickBina's commercial renovation permit guide explains what is needed.
  • Mall or landlord requirements: deposits, approved-contractor fees, after-hours works.
  • Reinstatement at the end of the lease, which some leases require.
  • Making good to damaged common areas.
  • Assumptions such as 'existing services in good condition' or 'no structural works'.

Red flags in a fit-out quote

  • A single lump sum with no breakdown, or a breakdown that does not add up.
  • Round-number rates across every trade, which usually means the job was not measured.
  • A total far below the others with no explanation of what was left out.
  • Large provisional sums covering work that is already defined on the drawings.
  • No programme, or one that ignores the approvals and the mall's working hours.
  • A payment schedule front-loaded far ahead of the work.

Compare the programme and payment terms too

Two quotes at the same levelled price are not equal if one opens your shop weeks later. Compare the programme, the payment schedule and how changes will be priced. A contractor who prices variation orders from the BQ rates gives you a benchmark for every change; ClickBina's variation order guide explains why that matters once work starts. The contract terms themselves, such as retention and the defects period, are a separate read.

How ClickBina can help

WhatsApp us your job details for a quote: the premises, the drawings or BQ you have issued, and the target opening date. ClickBina is an experienced KL & Selangor contractor for whole-house refurbishment and trade coordination, and can price against your package as issued, with any alternatives listed separately. We reply within the hour, and the price we agree is a flat price with no hidden charges. A site visit is RM150, waived if you go ahead.

Sources & methodology

  • ClickBina guide to reading a renovation quote — comparing quotes item by item, not total against total.
  • ClickBina guide to protecting a renovation budget — what a bill of quantities does and why to insist on one.
  • ClickBina commercial fit-out process, commercial renovation permit and variation order guides — tender basics, common exclusions, approvals and pricing changes.

About this page: it describes a levelling method and quotes no prices for fit-out work, because a fair comparison depends entirely on the scope you issue. The worked table shows patterns, not real bids.

Ready to get it sorted?

WhatsApp us your job details for a quote — we reply within the hour.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

Common Questions

How do I compare fit-out quotes fairly?
Issue one tender package, then level the quotes line by line: add back omitted items, align quantities and specifications, and use the same provisional sums before comparing totals.
What is a bill of quantities?
A list of numbered work items, each with a description, quantity, unit and rate, so every bidder prices the same thing.
What are provisional sums and prime-cost sums?
A provisional sum is an allowance for work not yet defined; a prime-cost sum is an allowance for an item still to be chosen. Use the same values for every bidder.
What are preliminaries in a fit-out quote?
The costs of running the job rather than the work itself, such as supervision, protection, disposal, insurance and cleaning.
Should I just take the cheapest quote?
Only after levelling. The cheapest raw total is often the one with the most exclusions.
What exclusions are common in fit-out quotes?
Approvals, professional fees, landlord deposits, equipment and signage, plus mall requirements and reinstatement.
Why does the BQ matter after the contract is signed?
Its rates become the benchmark for pricing variation orders when the scope changes.