Breakdowns rising and parts getting scarce? Here is how a committee decides between modernising and replacing its lifts, and how to run the project.

Lift modernisation replaces the parts of an ageing lift that wear out or become obsolete — usually the controller, drive, door equipment and fixtures — while keeping the shaft, rails and often the car frame; full replacement swaps the whole lift. Modernisation is usually the cheaper and faster route when the structure is sound; full replacement makes sense when the machine, rails and car are all worn, or the building wants a different lift type. Either way it is a sinking-fund project that needs a proper tender and DOSH approval. For comparison, ClickBina's lift maintenance guide lists a comprehensive maintenance contract at RM1,000 – RM2,500 per lift per month (indicative 2026).
A lift is several systems in one: the machine that moves it, the controller that decides where it goes, the drive that powers the motor, the doors and door operators, the car and its fixtures, and the guide rails, ropes and safety gear in the shaft. They age at different rates. Modernisation replaces the systems that are worn or obsolete and keeps the ones that are still sound. Full replacement removes everything down to the shaft and installs a new lift.
| Modernisation | Full replacement | |
|---|---|---|
| What changes | Controller, drive, door operators, fixtures; sometimes the machine and ropes | The whole lift, down to the shaft |
| What stays | Shaft, rails, often the car frame and counterweight | The shaft (sometimes altered) |
| Disruption | Each lift out of service for the works | Each lift out of service for longer |
| When it fits | Structure sound, controls and drive obsolete | Machine, rails and car all worn, or a different lift type wanted |
| Approvals | Alteration approved and certified | New installation approved and certified |
None of these alone decides the question. Together they tell the committee it is time to commission an independent assessment rather than keep paying for repairs.
The contractor who maintains the lifts is not a neutral adviser on whether to replace them. Before any proposal is priced, ask an independent lift consultant or engineer to inspect each lift and report on the condition of the machine, ropes, rails, controller, drive, doors and car, and to recommend which items to replace now, which later and which not at all. The report becomes the basis of the tender, so every bidder prices the same scope.
ClickBina's lift maintenance cost guide calls proprietary lock-in the most significant structural cost issue in lift maintenance: when a maker installs software, controllers or parts that only it can service, the building has little choice of maintenance contractor. The same guide notes that, for lifts nearing major overhaul, modernising the controls and drive to non-proprietary components can reduce long-term maintenance costs enough to justify the outlay.
In Malaysia, lifts are regulated as machinery under the Factories and Machinery Act 1967, with the Department of Occupational Safety and Health (DOSH) as the regulator. Every lift must be inspected periodically and hold a valid Certificate of Fitness. Any major repair, alteration or modification must also be approved, as the lift maintenance guide sets out. A modernisation is an alteration, so the contractor's scope should include the submissions, the inspection and the handover of the new certificate.
Put the approvals in the contract as the contractor's responsibility, with a clear date by which each lift must be back in service with its certificate.
A building with two or more lifts can usually modernise one at a time, but the remaining lifts carry every resident and every renovation load while the works run. Plan for it:
ClickBina's lift guide notes that major overhauls, rope replacements, motor rebuilds and full modernisation programmes are typically funded from the sinking fund, which is why the fund must be adequately maintained. If the fund cannot cover the project, the committee may need owners' approval for a special levy at a general meeting. Present the independent assessment, the options and the tender results together, so owners can see why the chosen route is worth the money. Our JMB tender guide explains when approval at a general meeting is needed.
There is no ClickBina published price for lift modernisation or replacement; it is quoted per lift after assessment. What the committee can compare is what the lifts cost to maintain now. These monthly fees per lift are quoted from ClickBina's lift maintenance guide (indicative 2026, Klang Valley).
| Contract type | Typical monthly fee per lift | What it covers |
|---|---|---|
| Scheduled maintenance only | RM300 – RM600 | Fixed-schedule visits; parts billed separately |
| Non-comprehensive (labour only) | RM600 – RM1,000 | Servicing labour; parts and major repairs billed separately |
| Comprehensive (parts and labour) | RM1,000 – RM2,500 | Most parts and call-outs included |
WhatsApp us your job details for a quote — we reply within the hour.
💬 WhatsApp for a quoteAdd up what each lift has cost over recent years in contract fees plus repairs billed outside the contract. That history, next to the tender prices, is what makes the case for or against modernising.
Lift works often come with related common-area jobs: lift lobby finishes, landing surrounds, ceiling and lighting upgrades, or making good around new equipment. These can be scoped and quoted separately from the lift contract.
Lift equipment is supplied and installed by specialist lift contractors. For the related common-area works around a lift project, WhatsApp us your job details for a quote: the building, the number of lifts and what is planned. ClickBina is an experienced KL & Selangor contractor for whole-house refurbishment and trade coordination. We reply within the hour, the price we agree is a flat price with no hidden charges, and a renovation site visit is free, and a repair inspection is RM180, deducted from the bill if you go ahead.
How we estimated prices: the RM figures on this page are monthly maintenance fees quoted unchanged from ClickBina's lift maintenance guide (indicative 2026, Klang Valley). Modernisation and replacement are priced per lift after assessment, so no project price is printed.