Smart Home for a New Condo at Key Collection
DLP-Safe Installs and the Right Order of Jobs

You have the keys and an empty unit. Here is how to plan the smart home without weakening your defect claims: what can go in now and what should wait.

📍 We serve KL, Selangor & Putrajaya.

Keys, an inspection checklist and a smart hub with boxed sensors in an empty new condo

Key collection is a good time to plan a smart home for a new condo, but not to drill first and ask later. Inspect the unit and report defects to the developer before anything is fixed to a wall, get the management’s approval for any works, then start with devices that leave the developer’s work untouched: a hub, battery sensors, an IR blaster and plug-in devices. Leave switch swaps and drilling until the electrical defects are closed and the dates are on record. For the wider picture, start at the smart home hub.

Why key collection is the moment to plan

An empty new unit is the easiest place to set up a smart home. There is no furniture to move, the walls are clean, and you can stand in each room and decide where the hub, the router and the sensors should go. Many owners also want the place working before the family moves in, so the aircon can be scheduled and the door can be checked from the office.

The catch is timing. A new home bought from a developer comes with a defect liability period, and the first weeks after vacant possession are when most owners inspect, report and chase repairs; the vacant possession handover guide explains what happens on the day you collect the keys. A smart home plan that ignores that process can make defect claims harder. A plan that works with it costs nothing extra and simply puts the jobs in the right order.

The defect liability period, in one paragraph

ClickBina’s defect liability period guide explains when the period starts, what it covers and how to report a defect in writing. The part that matters for smart devices is what the period does not cover. ClickBina’s guide to renovating during the DLP lists damage caused by the buyer, unauthorised renovations and improvements the buyer adds after handover among the exclusions. Anything you change in the unit therefore becomes something the developer may point to when a defect appears nearby.

That does not mean you must wait for the whole period to end before adding a single sensor. It means doing the defect work first, keeping your own additions separate and visible, and choosing installs that do not disturb walls, pipes or wiring until the developer has finished its repairs. Check the terms in your own sale and purchase agreement for anything specific to your project.

The order of jobs after vacant possession

StepWhat to doWhy it comes here
InspectWalk every room with a checklist and photograph everythingDefects found later are harder to pin on the developer
Test the electricsTry every socket, switch and the RCCBSmart switches will sit in these boxes later
Report in writingSend the defect list to the developer and keep proof of sendingStarts the developer’s repair clock
Get approvalApply to the management for any renovation or drillingMost new buildings require it
NetworkDecide the router position and test WiFi in every roomEvery smart device depends on it
Smart devices, no drillingHub, battery sensors, IR blaster, plug-in devicesLeaves the developer’s work untouched
Fixed installsLocks, switches, anything screwed or wired inAfter the related defects are closed

The new condo VP inspection checklist covers the first step room by room, and the guide to testing every power point at VP covers the second. Do both before you plan a single smart switch.

Installs that leave the developer’s work alone

Sort every device on your list by how it is fixed in place. The fewer holes and wires, the less it can be confused with a defect.

DeviceHow it is usually fixedTouches the developer’s work?When to do it
HubStands on a shelf, plugged into an existing socketNoFrom day one
IR blaster for aircon and TVStands on a shelf or cabinetNoFrom day one
Door, window and leak sensorsAdhesive pads or simply placed on the floorBarely; adhesive can mark paintFrom day one, after photographing the surface
Smart plugsInto existing socketsNoAfter the sockets pass your test
Mesh WiFi pointsOn a shelf or tableNoFrom day one
Clip-on curtain driverRides your own curtain trackNo, if you put the track up yourselfAfter the curtains go up
Smart lock on the main doorDrilled into the doorYes, the door and frameAfter door defects are closed and the management agrees
Smart wall switchesIn the existing switch boxesYes, the electrical installationAfter electrical defects are closed
Video doorbell or cameraScrewed to a wall, sometimes outside the unitYes, and possibly common propertyAfter management approval

Drilling during the defect period

Most new condo walls hide conduits and water pipes, and some are structural. A screw in the wrong place can start a leak or a fault that shows up months later, and at that point it is hard to prove whether the developer’s work or your screw caused it. The condo smart home guide sets out the building by-laws on drilling near concealed pipes and conduits.

  • Prefer devices that stand on a shelf or stick on with adhesive pads for the first months.
  • If something must be screwed in, ask the management for the as-built plans and use a detector before drilling.
  • Photograph and date the wall before and after every hole, with a tape measure in the frame.
  • Keep a simple list of every hole and fixing, so a later leak or crack can be checked against it.

Smart switches in a brand-new unit

Swapping the developer’s switches for smart ones is the change most likely to blur a defect claim, because it opens the electrical installation the developer is responsible for. If a socket or light point fails a test at VP, report it and let the developer fix it first. Once the electrical items on your defect list are closed and recorded, the swap can go ahead. Keep the original switch plates in case they are needed for a later inspection.

Swapping a wall switch is electrical work. For smart switches and anything wired into the mains, we supply the devices and set up the app, and the switch or wiring work is done by an electrical contractor registered with Suruhanjaya Tenaga that we coordinate. Any mains electrical work, such as a new power point, a change at the distribution board or a hardwired switch that needs new wiring, must be done by an electrical contractor registered with Suruhanjaya Tenaga.

The main door and the grille

A smart lock is often the first thing a new owner wants, and it is also the install most bound by rules. Many condo main doors are fire-rated, and the management may have a view on what can be fitted. Close any door and frame defects first, then check with the management before drilling. The guide to smart locks on fire-rated condo doors explains what to ask and which lock types suit.

Network first: router position and WiFi

A new condo usually comes with the fibre point wherever the developer put it, often in a corner of the living room or inside a cabinet. Before buying devices, decide where the router will live, then walk the unit with your phone and check the signal in every bedroom and at the main door. Devices bought before this check tend to end up in dead spots.

If you are planning carpentry, a TV cabinet or a store room, this is the time to give the router a proper home; the guide to network cabinets and router placement covers ventilation and position.

If you are renovating before moving in

Owners who plan a false ceiling, built-in carpentry or extra lighting should treat the smart home as part of that renovation, not an afterthought. Cable routes, switch box sizes and hub positions are far easier to settle before the ceiling closes; the smart home prewiring guide lists what to plan. The same rule applies as for any renovation during the defect period: let the developer repair first, then let your contractor start on surfaces that are recorded as accepted.

Records to keep from day one

  1. The vacant possession letter, your defect list and every reply from the developer, in one folder.
  2. Dated photos of each wall, door and switch before any device goes in.
  3. A list of every smart device, where it is, how it is fixed and who fitted it.
  4. Management approvals and any conditions attached to them.
  5. The app accounts, in a household member’s name, with a second adult invited.

When the unit is ready for daily life, the starter setup guide helps you choose the first handful of devices without overbuying.

How ClickBina helps

We install hubs, sensors, IR blasters, mesh WiFi, plug-in devices and battery curtain drivers in new units, starting with the installs that leave the developer’s work alone. We do the smart device, app and low-voltage side of the job. If your defect list is not done yet, we can plan the setup now and schedule the fixed installs for after the repairs.

Sources & references

  • Guides on this site on the defect liability period, renovating during the DLP, the new condo VP inspection checklist and testing power points at VP (linked in the text above).
  • Guides on this site on condo smart homes, smart locks on fire-rated doors and planning a smart home during renovation.
  • Your own sale and purchase agreement and the building’s house rules, for terms specific to your project.

Ready to set up your smart home?

WhatsApp us your job details for a quote — we reply within the hour. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

Common Questions

Can I install a smart home right after key collection?
You can start with devices that stand on a shelf or stick on, such as a hub, sensors and an IR blaster. Leave drilling and switch swaps until the related defects are reported and repaired.
Will installing smart switches affect my defect claims?
It can make electrical defects harder to pin on the developer, because the installation has been opened. Report and close electrical defects first, and keep records of the swap.
Is it safe to drill into a new condo wall?
Walls can hide conduits and pipes. Get the management’s approval, check the as-built plans, use a detector and photograph before and after.
Should I wait until the defect period ends before setting up a smart home?
Not for everything. Battery and plug-in devices can go in early; fixed installs are better timed after the related repairs.
Can I fit a smart lock on a new condo main door?
Often, but many main doors are fire-rated and the management may have rules. Close door defects and ask first.
What should I set up first in a new condo?
The router position and WiFi coverage, then a hub and a few battery sensors.
Do I need the management’s approval for smart devices?
Not usually for devices that stand on a shelf or plug in. Drilling, door changes and anything outside the unit generally need it; check your building’s rules.