An uneven screed turns into squeaking planks, open joints and hollow tiles. How to check flatness, level, height and soundness while the fix is still a day's work.
📍 We serve KL, Selangor & Putrajaya.

Before vinyl, SPC, laminate, timber or large tiles go down, the floor screed should be checked for three things: that it is flat enough for the flooring maker's tolerance, that it sits at the right height at doors and junctions, and that it is sound and dry. A straightedge, a string line and a torch find most problems in an hour. A dip found now is filled in a day; found after the floor is laid, it means lifting the floor. To have the screed checked by someone outside the job, see renovation inspection.
Owners and contractors often say "level" for all three, which is how arguments start. They are separate questions, and a floor screed can pass one and fail another.
Before you check anything, ask the contractor which of the three each area was screeded for, and what finish is going on top. The answer decides which test matters in each room.
Once a floor is down, the screed is out of sight and the arguments begin. Click planks that squeak or open at the joints, tiles that sound hollow along one line and doors that scrape the new floor all start as screed problems, but after installation they look like flooring problems, and the flooring installer and the screed contractor may each point at the other. Checking the bare screed, with both trades told the result, gives one clear moment when responsibility passes from one to the next.
It also matters for the flooring's own terms. Several flooring makers tie their product warranty to the subfloor meeting their instructions, so collect the installation sheet for the product you bought and keep it with your renovation file.
There is no single flatness figure for every floor. The number that matters is the one in the installation instructions of the flooring you are laying, and different makers ask for different things. Two published examples for rigid-core SPC show the point:
| Source | Flatness asked for | How it reads in practice |
|---|---|---|
| Wickes / Verona ClickLux SPC instructions | Max 3mm within 2m | Tighter: a short straightedge check |
| MSI hybrid rigid core installation guide | 5mm per 3 meters | Measured over a longer span |
| Your contract or flooring supplier | Ask for the figure in writing | This is the one your job is judged on |
For tiles, timber and other floors, ask the tiler or supplier what the screed must achieve before they start, and agree it before the screed is laid rather than after. A screed contractor who knows the target can work to it; one who was never told can only guess.
A long spirit level or a straight aluminium bar is the basic tool. Sweep the floor first, because a grain of sand under the bar gives a false reading. Lay the bar flat on the screed and look at the gap underneath, with a torch on the far side if the room is dim. Repeat in a grid across the room and in two directions, paying extra attention near walls, at doorways and wherever two screed batches meet.
Mark each spot where light shows under the bar, and push a coin or a set of feeler cards under the gap to get a feel for its size. Rock the bar too: if it pivots on a point, there is a hump, which needs grinding rather than filling. Write the result next to a quick sketch of the room so the contractor can find each spot again.
A straightedge shows short dips; it can miss a gentle rise across the room. MSI's installation guide describes a simple method that needs only a nail and a length of string: fix the string at the centre of the floor with the knot pressed to the surface, pull it tight to the far side, and look for high and low spots relative to the string.
Two people make this easier. One holds the string tight against the floor at each wall in turn while the other walks along it looking for points where the screed touches the string or falls away from it. For a level check over a whole house, a contractor will often use a water level or a laser level; ask them to show you the readings at the corners of each room.
Flatness is only half the job; the screed also sets where the finished floor will end up. Add the thickness of the flooring, its underlay and any adhesive to the screed height and check what that does at each door, the main entrance, the sliding door to the balcony and the line where new floor meets old tiles in a room you are keeping. Doors may need trimming, and a step at a junction needs a transition strip or a ramp profile that suits the product.
In condos, also check the height at the main door against the corridor and the height of the balcony floor against the door sill. Raising either too far can mean water running inwards in heavy rain, so ask before the screed is laid, not after.
A flat screed can still be a weak one. Run a key or a nail firmly across the surface in a few places: a sound screed scratches lightly, while one that crumbles or leaves a deep groove may be too weak for glue-down floors or tile adhesive. Tap it with a hammer handle and listen for hollow areas, just as you would with tiles. Look for cracks, especially along door lines and over pipe runs, and for dust that rubs off on your hand. Any loose patch, and any area that sounds hollow, should be raised with the contractor before flooring covers it.
Moisture is the check that cannot be done by eye. A freshly laid screed holds a lot of water, and moisture coming up from below is a common reason a new floating floor lifts or a glue-down floor bubbles. MSI's installation guide, for example, says new concrete needs to be cured for at least 60 days before its flooring is installed.
Screeds and products differ, so ask the flooring supplier how they want dryness confirmed and what reading they accept, then ask the installer to test it before laying. If the programme is tight, ask whether a moisture barrier or a specific primer is required for that product, and get the answer in writing.
In a bathroom, wet kitchen, yard or balcony the screed check is about direction rather than flatness. Pour a little water on the bare screed, or roll a marble across it, and see that it heads towards the floor trap from every corner. Check that the trap body sits at the low point and that the screed around it is not higher than the trap rim. If water stands or runs the wrong way, the fix belongs in the screed before waterproofing and tiling; wrong bathroom falls shows what happens when it is left.
| Check | How | Sign of a problem |
|---|---|---|
| Flatness | Straightedge in a grid, two directions | Light or a coin gap under the bar; bar rocks on a hump |
| Room-wide level | String line, water level or laser readings | Screed touching or falling away from the line |
| Heights | Screed plus flooring thickness at each door | Door will scrape; step at a junction |
| Surface strength | Scratch with a key or nail | Crumbling surface or deep groove |
| Hollow areas | Tap with a hammer handle | Dull, drummy sound over an area |
| Cracks and dust | Look and rub by hand | Open cracks, powder on your palm |
| Dryness | Supplier's stated test, done by the installer | Reading outside what the supplier accepts |
| Falls in wet areas | Water or a marble on the screed | Water stands or runs away from the trap |
Most screed faults have straightforward fixes if they are found before the floor goes down: humps are ground off, dips are filled with a patching compound, and a wavy floor over a large area may need a self-levelling compound. Which product suits which floor is covered in floor screed and self-levelling compound. Ask for the fix to be checked again with the same straightedge before the flooring installer starts, and do not accept the flooring trade levelling the floor with extra underlay unless the product's instructions allow it. For the check after the planks go down, see SPC and vinyl flooring installation check.
A screed check is quick, but it has to happen in the short gap between the screed drying and the flooring arriving. We can come in that gap, check the screed against your flooring's installation sheet and your quotation, room by room, and go through what we found with you before the floor is laid. Third-party inspection of your contractor's work; if you want, we can also quote the repairs.
These are manufacturer requirements for specific products, shown as examples. Follow the installation instructions for the flooring you are laying, and the figures agreed in your contract.