A newly tiled floor looks perfect on the day it is cleaned. How to tap, light and measure it so hollow tiles, stepped edges and poor joints are found while the tiler is still on site.
📍 We serve KL, Selangor & Putrajaya.

New tiling is checked in four passes: tap every tile for hollow spots, run a straightedge and a low torch beam across the joints for lippage, look along the grout lines for gaps and uneven width, and pour water on wet floors to see that it reaches the trap. Do it once the adhesive has set and before the final tiling payment, while the tiler is still on the job. Hollow tiles and stepped edges are far easier to put right in week one than in year two. To have the tiling checked by someone who did not lay it, see renovation inspection.
Timing changes what you can see and what it costs to fix. Checking too early, while the adhesive is still green, can make sound tiles feel loose; checking too late, after furniture, a kitchen cabinet or a vanity has gone on top, hides the very tiles most likely to have been rushed. The useful windows are these:
None of this needs special equipment. A coin, a wooden spoon handle or the plastic end of a screwdriver works for tapping. A long spirit level or any straight aluminium bar does for a straightedge. A phone torch held at floor level shows edges that look flat in daylight. Add a roll of masking tape to mark faults, the tile box (for the batch and shade code), and your quotation and layout drawing so you can compare what was laid with what was agreed.
A tile that is fully bedded gives a short, solid click when tapped. Where the adhesive has not made contact, the sound turns dull and drummy, and on large tiles you can often hear exactly where the solid part stops. Work in a pattern so nothing is missed: start in one corner, tap each tile at its centre and near each of its corners, then move along the row. Mark every hollow one with a small square of tape and write the room and count on your sheet.
Pay most attention to tile edges and corners, where a partly hollow tile chips first, to doorways and corridors that take the most foot traffic, and to anything that will carry weight, such as the spot under a fridge or a kitchen island. A cluster of hollow tiles along one line usually points to a dip or hump in the floor below, not just one careless tile. Tiles stuck down on a few blobs of mortar rather than a full bed are a common cause, and the method is explained in tile adhesive versus cement-sand mortar.
This is the question most owners search for, and there is no honest single answer to give on a web page. CIDB's QLASSIC standard, CIS 7, treats hollowness and delamination of floor finishes as one of the defect groups an assessor checks, but the criteria are set out in the standard itself, and your renovation contract may say something different or nothing at all.
The practical approach is to agree it before the work starts. Ask the contractor to state in writing what they will treat as a hollow tile to be relaid, for example any tile that sounds hollow at a corner or across a stated part of its face, and whether that changes for large tiles. Where you want to tie the job to a published standard, renovation workmanship tolerances and QLASSIC explains how to write that into the contract.
Lippage is a step between the edges of two neighbouring tiles. Small steps catch dirt and bare feet and look worse every time light comes in low through a balcony door. Lay the phone torch on the floor and shine it along the surface: raised edges throw a thin shadow line. Then rest the straightedge across the joint at the worst spots and slide a fingernail or a thin card along it to feel for steps.
Flatness is a different check from lippage: a floor can have neat joints and still rise and fall across the room. Lay the straightedge in several directions in each room and look for gaps under it. Large and long tiles show both faults more than small ones, because a slight bow along a long tile turns into a visible step at the joint, as large-format tile installation explains. Ask the contractor what allowance they work to and get it in writing before you judge the result against it.
Grout is easy to judge by eye if you know where to look. Kneel down and look along a grout line rather than straight at it. The things that matter are:
Layout faults are not leaks or loose tiles, but they are the ones you will look at every day. Check that the tile direction, pattern and starting line follow the drawing you approved. Narrow slivers of tile at a doorway or along the most visible wall usually mean the layout was not set out from the centre of the room. Look for joints that line up where they should, from the floor into the wall in a bathroom and through doorways between rooms. Open two or three of the remaining tile boxes and compare the batch or shade code with the laid tiles; a noticeable change in shade from one area to the next often comes from mixed batches.
In bathrooms, wet kitchens, yards and balconies the tile check includes water. Pour a bucket slowly across the floor and watch where it goes. It should run to the floor trap without standing in a corner or against the door. Check that the tiles around the trap are cut neatly to the trap rim, and that no grout has been smeared into the grating. Water that sits still after a few minutes is a falls problem in the screed under the tiles, not something more grout will fix.
| Check | How to do it | What to note |
|---|---|---|
| Hollow tiles | Tap centre and corners of every tile | Room, count, tile marked with tape |
| Lippage | Low torch beam, then straightedge across the joint | Location of each step you can feel |
| Flatness | Straightedge in several directions | Where the gap under the bar is largest |
| Grout | Look along the joint line | Gaps, pinholes, colour patches, haze |
| Edge and movement gaps | Look at walls, columns and long runs | Tiles tight against walls with no gap |
| Layout | Compare with the approved drawing | Slivers, wrong direction, misaligned joints |
| Shade | Compare box codes with laid tiles | Areas with a visible change in shade |
| Falls in wet areas | Pour a bucket across the floor | Where water stands and for how long |
It helps to know which faults are common even on professionally built projects. CIDB's technical report on QLASSIC defect data from 2015 to 2018 groups floor defects into finishing, alignment and evenness, cracks and damage, hollowness and delamination, and jointing. Its 2018 figures show how often floors complied in each group on the projects assessed:
| Floor defect group (QLASSIC) | Compliance reported for 2018 | What it suggests for your check |
|---|---|---|
| Alignment & Evenness | 99.5% | Usually fine on assessed projects; still check large tiles |
| Crack & Damages | 96.2% | Look for chipped edges from other trades after tiling |
| Hollowness / Delamination | 63.0% | Tap every tile; this group fails far more often |
| Finishing | 35.1% | Look at grout haze, stains and surface finish |
| Jointing | 15.1% | Look closely along every grout line |
These figures come from assessed building projects, not home renovations, so read them as a guide to where tiling tends to fall short rather than as a score for your contractor.
Put what you found in one written list, with each item tied to a room and a tile you have marked, and send it before the tiling payment is released. Ask which items will be relaid, by when, and how the replacement tiles will be matched; this is why it pays to keep spare boxes from the same batch. Relaying a hollow tile on a new floor is a small job while the tiler is still on site. If the tiles in question are years old rather than new, the causes and repairs are different, and popped and hollow old floor tiles covers those.
If you would rather not crawl across every room with a coin, we can do the tile check for you. We walk the floors and walls against your quotation and layout drawing, room by room, and go through what we found with you before the tiling payment. Third-party inspection of your contractor's work; if you want, we can also quote the repairs.
Hollowness and lippage allowances are not quoted on this page. Agree them with your contractor in writing, or refer to the standard named in your contract.