Renovation Permit MBDK (Klang)
Pelan Setara or a Consultant Plan, Fees & Timing

Two routes: the owner’s pelan setara book for single-storey additions, or a consultant’s plan for the rest.

📍 We serve KL, Selangor & Putrajaya.

Klang house with a rear brick extension under construction, scaffold and cement bags on site

Renovation that needs approval from MBDK (Majlis Bandaraya Diraja Klang, the former Klang Municipal Council) goes one of two ways: the owner buys MBDK’s pelan setara standard-plan book for common additions to a single-storey house, or a qualified consultant submits a renovation plan. MBDK’s client charter decides complete alteration and addition applications in one day for homes and seven days for non-residential buildings. The pelan setara book costs RM10, and the bill on the pelan setara checklist lists a RM100 plan fee, a RM100 plan deposit, RM308 for placing building materials and RM700 for two roro bins.

The two MBDK routes for home renovation

MBDK’s Building Department (Jabatan Bangunan) has a division just for renovation control, the Bahagian Kawalan Kerja Ubahsuaian. It processes renovation plans either through a consultant or through the pelan setara book, and after approval it issues a work completion certificate (Perakuan Siap Kerja) for the alteration. The route depends on how big the job is:

RouteWhat it suitsWho appliesTiming on MBDK’s documents
Pelan setara bookStandard front, rear and side extensions, fences and small items on a single-storey houseThe house owner (only the owner may buy the book)Within 24 working hours, or immediately, for housing; 7 days otherwise
Renovation plan (checklist PS2024)Anything outside the standard plans, and additions above one storeyA qualified consultantCharter: one day for homes, seven days for non-residential
Small alteration works permit (OSC checklist)Listed on the OSC forms page; the checklist is a scanned documentAsk at the OSC counterNot stated in readable form

Klang became a royal city council with effect from 23 November 2023, declared on 5 February 2024, so older papers still say Majlis Perbandaran Klang. Not every address with a Klang postcode is administered by MBDK, so check the council named on your assessment bill first. The Klang area page covers the town itself, and the national rules are in ClickBina’s renovation permit guide.

The pelan setara book

Pelan setara are MBDK’s ready-made drawings for the additions owners ask for most. The book costs RM10 and only the house owner may buy it. The explanation sheet that comes with it says a renovation of a single-storey house can use the book, while an addition above one storey must go through a qualified consultant. The standard plans listed on the checklist include:

  • Terrace house front extensions in two designs (PSRT 1.1 and PSRT 1.2), a rear extension (PSRT 2) and side extensions (PSRT 3).
  • Plans for semi-detached houses (PSRB) and bungalows (PSRS).
  • Small items: a driveway culvert, a bin chamber, a fence (PSP 3), sanitary fittings and roofing over an air well (PSP 5).

Two cases need more than the book. A side or rear addition with a reinforced-concrete flat roof needs a plan, structural calculations, Form A and a certificate from a consulting engineer, and breaking a party wall needs an engineer and fire department support. A rear kitchen extension with a pitched roof is the typical book job.

Setbacks the pelan setara book enforces

The explanation sheet sets the open space an extension must leave. These are the figures it prints:

SituationSetback on the MBDK sheet
Rear extension of a terrace house where the back lane is 10 ft wide or less1 m left open
Side and rear of a semi-detached house or bungalow10 ft with no building at all
Front addition with walls20 ft
Front roof that is fully closed10 ft

Terraces in Bukit Tinggi, Bukit Raja and Kota Bayu Emas with back lanes only 10 ft wide are handled differently: the addition comes under a temporary building permit (Permit Bangunan Sementara), and the owner signs an undertaking to demolish it when required, subject to appeal. That permit costs RM100 and is paid every year.

Fees printed on MBDK’s forms

MBDK’s forms disagree in places, so each figure below is given with the form it comes from. Treat them as the council’s published figures and confirm the bill at the counter:

ChargeAmountWhere it appears
Pelan setara bookRM10Book-purchase explanation sheet
Plan or permit fee, pelan setaraRM100Pelan setara checklist and explanation sheet
Plan deposit, pelan setaraRM100Pelan setara checklist
Plan deposit, renovation plan through a consultantRM200Checklist PS2024
Placing building materialsRM308Both checklists
Roro bins for construction wasteRM350 a bin: RM700 for two (pelan setara), RM1,050 for three (PS2024)Roro bin form and both checklists
Roro bin deposit, where it appliesRM500Both checklists
Temporary building permit, back-lane terracesRM100 a yearPelan setara checklist

Want this priced for your home?

WhatsApp us your job details for a quote — we reply within the hour. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

For plans submitted through a consultant, MBDK’s general building-plan fee schedule charges the ground floor at RM14 per 9 m², with a minimum of RM140; the PS2024 checklist refers to a fee calculation format without printing it, so the consultant confirms the exact plan fee. Shop-office renovations that need council parking bays pay RM90 a bay, at least two bays, with a RM90 deposit a bay and a hire of up to two weeks.

Documents for a pelan setara application

  • The permit application form for minor construction, alterations and small additions in lieu of plans.
  • The latest paid assessment and quit-rent bills.
  • Form F for housing built from 2007, a copy of the certificate of fitness, or the land title for older housing.
  • A location plan from Google Map with coordinates.
  • Dated colour images of the house, taken within three days of the application.
  • A copy of the appointed contractor’s registration certificate (see the contractor section below).
  • For back-lane terraces in Bukit Tinggi, Bukit Raja and Kota Bayu Emas, the signed undertaking for the temporary building permit.

The consultant route: checklist PS2024

Everything outside the standard plans goes through a consultant using MBDK’s renovation-plan checklist PS2024. The consultant’s company and board registration certificates go in with the plans, along with the owner’s identity card copy. Two letters protect the neighbours: a notification letter to the houses next door, and the owner’s undertaking to repair any damage. MBDK says the undertaking is a condition of approval for front, car porch, side or rear extensions and new boundary fences, while the neighbour letter is only for information and is not mandatory, for example when neighbours cannot be reached.

Building-plan work through OSC 3.0 Plus Online is submitted with every document in PDF. MBDK’s building-plan checklist also asks for a site board showing the consultant, the contractor and the MBDK file reference before construction starts, a permit before any hoarding goes up, and Forms B, C and D four days before each stage of work, with a compound if they are late.

Bins, fences and the site

  • Roro bins come from MBDK’s environmental services department (Jabatan Perkhidmatan Persekitaran). The owner applies seven days before the renovation starts, and a bin may stay on site no more than 14 days, public holidays included.
  • To get the bin deposit back, the owner shows the receipt for disposing of the waste at the Jeram sanitary landfill. The debris and roro bin guide covers the practical side.
  • Fences shown on a renovation plan are limited to 1.7 m, an open fence needs openings of at least 40% of its surface, and every boundary wall or fence must sit inside the owner’s own lot.
  • MBDK does not publish site working hours for renovation, so follow your management office or ask the Building Department.

Condos, apartments and shop-offices

For a strata unit, the PS2024 checklist asks for a renovation permission letter from the Joint Management Body, a copy of its house rules and the receipt for its renovation deposit. Management approval sits on top of the council’s own rules, as the strata renovation rules guide explains. Shop-office jobs that need a lorry or a bin in front of the shop rent council parking bays at the rate in the fees section.

The contractor requirement on MBDK forms

Both the pelan setara checklist and checklist PS2024 ask for a copy of the appointed contractor’s certificate of registration with the Construction Industry Development Board. This is MBDK’s rule, printed on its own forms, so check with the Building Department how it applies to your job before you submit, and ask any contractor you are considering for the certificate.

Contacting MBDK and starting early

  • Renovation counter, as printed on the renovation forms: Jabatan Bangunan, Aras 2, Pusat Perniagaan Raya Barat, Jalan Raya Barat, 41000 Klang, tel 03-3375 7802.
  • Building Department email: bangunan@mbdk.gov.my. Council headquarters: Bangunan Sultan Alam Shah, Jalan Perbandaran, 41675 Klang, general line 03-3375 5555.
  • One Stop Centre (OSC): tel 03-3375 7873, email osc@mbdk.gov.my.
  • The online OSC link on MBDK’s site no longer works, so ask the OSC which portal to use before a consultant submits.

MBDK’s Building Department issues notices for building-work offences under the Street, Drainage and Building Act 1974. It does not publish a penalty amount for renovating before approval; the renovating without a permit guide explains how enforcement generally works.

How ClickBina fits in

ClickBina is an experienced KL & Selangor contractor. We do the renovation work and coordinate the trades, and plan the programme around MBDK’s bin, fence and setback rules. The MBDK application itself is made by the owner for the pelan setara book, or by a consultant for a renovation plan. WhatsApp us your area, house type and the work you have in mind; we reply within the hour, and the price we agree is a flat price with no hidden charges. The Bandar Botanic page shows how this works on one south Klang township.

Sources & official references

Ready to get it sorted?

WhatsApp us your job details for a quote — we reply within the hour. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

Common Questions

Who approves renovation in Klang?
MBDK (Majlis Bandaraya Diraja Klang), through its Building Department. Not every address with a Klang postcode is administered by MBDK, so check the council named on your assessment bill.
How long does MBDK take to approve a renovation?
MBDK’s charter decides complete alteration and addition applications in one day for homes and seven days for non-residential buildings; the pelan setara sheet says housing applications are approved within 24 working hours or immediately.
How much does the MBDK pelan setara cost?
The book is RM10. The pelan setara checklist bill lists a RM100 plan fee, a RM100 plan deposit, RM308 for placing materials and RM700 for two roro bins, plus a RM500 bin deposit where it applies.
Can I extend a double-storey house with pelan setara?
No. MBDK’s sheet says pelan setara is for renovating a single-storey house, and an addition above one storey must go through a qualified consultant.
How long can a roro bin stay outside my house in Klang?
No more than 14 days, public holidays included, under MBDK’s roro bin form. Apply seven days before work starts.
Does MBDK need my neighbour’s consent?
The neighbour notification letter is for information only and not mandatory, but the owner’s undertaking to repair neighbour damage is a condition of approval for front, side or rear extensions and new fences.
Does MBDK have rules about the contractor?
Yes. Its pelan setara checklist and checklist PS2024 ask for the appointed contractor’s certificate of registration with the Construction Industry Development Board.