Renovation Permit MBSA (Shah Alam)
What Needs Approval, How to Apply, Fees & Timing

Fence permit, the pelan setara book or an architect: which MBSA route fits your house and job.

📍 We serve KL, Selangor & Putrajaya.

Shah Alam terrace house with a new brick and grille front fence being finished

A renovation permit from MBSA (Majlis Bandaraya Shah Alam) depends on the job and the house: a residential alteration permit for a new fence, main gate or refuse chamber (RM648 including the permit to place materials), the pelan setara standard-plan book for additions to intermediate one- and two-storey terraces (RM300 per addition, approval in five working days), and plans by an architect or draughtsman registered with the Board of Architects for everything else. MBSA does not publish a general interior minor-works permit for tiles or ceilings, so ask the Building Department before assuming either way. Since 1 June 2024, consultant applications for house additions go through OSC 3 Plus Online.

How MBSA sorts home renovation

MBSA’s Building Department (Jabatan Bangunan) does not run one catch-all renovation permit. Each route is tied to a type of work and, for additions, a type of house:

RouteWhat it coversWho appliesTiming MBSA publishes
Residential alteration permitNew fence, main entrance, opening height and width, refuse chamberThe owner, at Counter 1Not published
Pelan setara (residential)Standard additions to intermediate one- and two-storey terraces with a CF or CCCThe owner, using the bookFive working days
Pelan setara (commercial)Partitions, awnings and party walls in shophouses and shop officesThe owner or tenantNot published
Additions and alterations (TP)Other house additions: bungalows, zero-lot, terraces, semi-Ds, clustersAn architect or registered draughtsman, via OSC 3 PlusNot published
Building planNew buildings, after planning permission and engineering plansArchitects and engineers30-day charter

The rules every council shares are in ClickBina’s renovation permit guide; this page covers MBSA only.

Interior work: what MBSA does and does not publish

Several councils publish a minor-works list for tiles, ceilings and similar interior work. MBSA’s website does not: we found no general interior minor-works permit and no published list of work that needs no permit. That is not the same as saying interior work never needs approval. Before you re-tile, hack a wall or add a plaster ceiling, ask the Building Department how it treats the job, and get the answer in writing if you can.

Anything structural, any new floor area and anything that changes the outside of the house is a plan submission. For condos and apartments, the management body’s own renovation rules apply on top.

Fences, gates and refuse chambers

MBSA’s residential alteration permit is specific to fences, the main entrance and the height and width of openings, and the form also covers the refuse chamber. Fill in the Borang Kebenaran Membina Pagar dan Kebuk Sampah, attach the application for a permit to place building materials and, if the work touches a perimeter fence shared with a neighbour, the neighbour’s consent letter, then submit at Counter 1 of the Building Department. MBSA gives two standard designs:

DesignHeightConditions
Brick wall with mild-steel grille900mm brick plus 600mm grillePlastered and painted on both faces; the grille gives light and ventilation
Brick wall1500mmPlastered and painted on both faces, with 40% openings for light and ventilation

The Kota Kemuning page covers gate width and culvert details on bigger plots.

Pelan setara for intermediate terraces

For owners of intermediate one- and two-storey terraces that already have a CF or CCC, MBSA sells a book of standard plans that replace consultant drawings under section 18 of the Uniform Building By-Laws 1984. You choose the addition, mark the house type, the part being extended, the lot size and the distance from the boundary, and sign every form and sketch with your name as it appears on the sale and purchase agreement, your address and IC number.

  • Apply for the permit to place building materials together with the plans.
  • Use MBSA’s RORO bin service for construction waste; it is required, and paid with the processing bill.
  • The owner is fully responsible for the stability and strength of what is built, and MBSA accepts no liability for claims arising from it.
  • Corner and end lots, houses already altered and designs not in the book go through the consultant route instead.

The Denai Alam page shows how the book fits a township of near-identical terraces.

Fees MBSA publishes

ChargeAmountRoute
Processing plus permit to place building materialsRM648Fence, gate and refuse chamber
Plan processingRM300 per additionResidential pelan setara
Permit to place building materialsRM648Residential pelan setara
RORO bin waste collectionRM880Residential pelan setara
Pelan setara guideline bookRM50Residential pelan setara
Partitions, awnings, party wallsPer space, per area of awning and per length of party wall, on MBSA’s pageCommercial pelan setara

Want this priced for your home?

WhatsApp us your job details for a quote — we'll reply as soon as we can. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply on WhatsAppFlat price, no hidden chargesExperienced KL & Selangor contractor

MBSA asks for the paid receipts to be handed in at the Building Department counter on the day you pay; without them the application is not processed.

Where and when to apply

  • Fence, gate and refuse chamber: Counter 1, Building Department, Wisma MBSA.
  • Residential pelan setara: the Building Department counter at Wisma MBSA, which takes complete applications Monday to Thursday 8am to 4.30pm, and Friday 8am to 11am and 3pm to 4.30pm.
  • Consultant additions (TP): through OSC 3 Plus Online since 1 June 2024; MBSA also gives a status-check link for these applications.
  • Payment: at the main counter, Lift A, ground floor, Wisma MBSA.

MBSA does not publish permitted working hours for home renovation on these pages, so check with the Building Department and, for strata homes, with your management office.

When you need an architect or draughtsman

Additions to bungalows, zero-lot bungalows, terraces, semi-detached and cluster houses that already have a CF or CCC are submitted as additions and alterations (TP) with plans certified by a professional architect or a draughtsman registered with the Board of Architects Malaysia. MBSA publishes setback tables for additions inside the building setback; the Setia Alam page explains how lot position changes the numbers, and the Bukit Rimau page covers adding a floor to a single-storey terrace.

Shophouses and shop offices

For commercial premises, MBSA has a separate pelan setara permit for partitions, awnings and party walls in shophouses and shop offices, which the owner or tenant can submit without a consultant using the commercial standard-plan book. Waste collection is billed separately by MBSA’s solid waste department. For a full fit-out, the commercial renovation permit guide covers the other approvals.

Starting before approval

MBSA’s pages cite section 70(1) of the Street, Drainage and Building Act 1974, which requires the council’s written permission before building work. Fines are added to the processing bill where they apply. The renovating without a permit guide explains enforcement and regularising work after the fact.

MBSA area guides

AreaWhat the page adds
Shah AlamThe Seksyen layout and MBSA charters
Shah Alam house renovationCosts for terraces, semi-Ds and condos
Rear kitchen extensionsThe most common terrace addition, step by step

How ClickBina fits in

MBSA’s permits are applied for by the owner, or by the architect or draughtsman for TP plans. ClickBina is an experienced KL & Selangor contractor: we do the renovation work and coordinate the trades, and we plan the job around MBSA’s bin, materials and site rules. WhatsApp us your area, house type and the work you have in mind; we'll reply as soon as we can, and the price we agree is a flat price with no hidden charges.

Sources & official references

Ready to get it sorted?

WhatsApp us your job details for a quote — we'll reply as soon as we can. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply on WhatsAppFlat price, no hidden chargesExperienced KL & Selangor contractor

Common Questions

Do I need an MBSA permit to build a new fence?
Yes. MBSA’s residential alteration permit covers new fences, the main gate and refuse chambers; the processing and materials permit together cost RM648.
Does MBSA have a minor-works permit for tiles and ceilings?
MBSA does not publish one on its website. Ask the Building Department how it treats your interior job before you start.
How long does MBSA take to approve a pelan setara application?
MBSA says it issues approval within five working days of receiving the application.
Can I use the MBSA pelan setara book for a corner terrace?
No. The book is for intermediate one- and two-storey terraces with a CF or CCC. Corner and end lots go through an architect or registered draughtsman.
How much does MBSA charge for a terrace addition under pelan setara?
RM300 per addition, RM648 for the permit to place building materials and RM880 for the RORO bin service. The book costs RM50.
What are MBSA’s renovation working hours?
MBSA does not publish them on its permit pages. Check with the Building Department, and with your management office if you live in a strata development.
How do I submit house additions to MBSA now?
Through OSC 3 Plus Online since 1 June 2024, with plans by a professional architect or a draughtsman registered with the Board of Architects Malaysia.
Do I need an MBSA permit for a partition wall?
For shophouses and shop offices, MBSA has a commercial pelan setara permit for partitions, awnings and party walls, which the owner or tenant can submit without a consultant using the commercial standard-plan book; the fee is charged per space. For a house, MBSA does not publish a minor-works permit or a list of interior work that needs no permit, so ask the Building Department how it treats your partition and get the answer in writing. In a condo, the management’s renovation rules apply on top.
How much does an MBSA renovation permit cost?
MBSA has no single renovation permit fee; it depends on the route. For a fence, gate and refuse chamber, processing plus the permit to place building materials is RM648. Under residential pelan setara, plan processing is RM300 per addition, plus RM648 for the permit to place building materials, RM880 for the RORO bin and RM50 for the guideline book. Commercial partitions, awnings and party walls are charged per space, per area of awning and per length of party wall.