A renovation permit from MPAJ (Majlis Perbandaran Ampang Jaya) for a condo or apartment interior is Borang 1A: a RM100 permit for grilles, wardrobes, kitchen cabinets, awnings and new tiles that do not change the original structure, signed off by the developer, JMB or MC, and processed within a 24-hour period once the application is complete. Additions and alterations to a landed house are different: you appoint an architect or registered plan drawer first, and MPAJ processes the application within 14 days. MPAJ does not publish a minor-works list for landed homes, or renovation working hours, in these documents.
MPAJ covers the Selangor side of Ampang, Pandan Indah and Pandan Jaya, Taman Melawati, Hulu Kelang and Bukit Antarabangsa. Its Building and Architecture Department (Jabatan Bangunan dan Senibina) publishes two clear routes for homes:
| Route | For | Who applies | Processing (MPAJ flowchart) |
|---|---|---|---|
| Borang 1A | Interior renovation of multi-storey (strata) homes without changing the original structure | The owner or tenant, with the developer, JMB or MC’s consent | 24-hour, once complete |
| Additions and alterations | Extensions and renovation of landed houses | An architect or registered plan drawer, appointed before applying | Within 14 days |
Not sure whether you are in MPAJ or DBKL? The council named on your assessment bill is the one that approves building work; parts of Ampang Hilir and Jalan Ampang are DBKL. The rules every council shares are in ClickBina’s renovation permit guide.
Borang 1A (revision 02, dated 1 November 2023) is MPAJ’s form for interior renovation without changing the original structure of a multi-storey home. It names the works it is meant for:
Anything that touches the structure, such as hacking a wall, moving a wet area or enlarging a balcony, is outside Borang 1A. Ask MPAJ and your management office before you plan it; structural work in a strata building also needs the management body’s consent for common property.
In practice the list fits the jobs most condo owners in Pandan Indah and Ampang actually plan: a kitchen refit with new cabinets and tiles, built-in wardrobes in the bedrooms, safety grilles on the windows and main door, and an awning over a balcony or yard where the building allows one. If your plan mixes listed items with something structural, split them: the listed items can go on Borang 1A, while the structural part needs its own advice and approval before anyone starts. Writing each item on the form as it will actually be built also avoids questions when MPAJ or the management office inspects.
| Charge | Amount | Notes |
|---|---|---|
| Borang 1A permit | RM100 | Printed on the form |
| Permit to place building materials in a public place | RM36 per square metre, at least RM108 | Back lane, five-foot way, road shoulder or road |
| Sticker, RORO bin and bin deposit | Lines on the bill; amounts not printed on Borang 1A | Charged where they apply |
| Fine | A line on the bill | Where work started without approval |
WhatsApp us your job details for a quote — we reply within the hour. A site visit is free. We serve KL, Selangor & Putrajaya.
💬 WhatsApp for a quoteBorang 1A’s office section lists fine, permit, materials permit, sticker, RORO bin, RORO deposit and other charges. Only the permit amount is printed, so ask the secretariat for the full bill before you commit to dates.
The management body’s signature is the item most often missing. Get it before you go to Menara MPAJ, because an incomplete application is sent back for more documents.
For a terrace, semi-detached house or bungalow, MPAJ’s flowchart for residential additions and alterations starts with appointing an architect or registered plan drawer; the owner cannot file this one alone. The consultant submits to the secretariat on level 4 for checking, MPAJ issues the bill, and the application is processed within 14 days once it is complete.
Fees for plans are worked out on floor area, and the landed form includes a neighbour notification letter. The Melawati page goes through both, and the Ampang page covers who may sign plans and the slope history that shapes hillside jobs.
Where MPAJ is silent, we say so rather than guess. A phone call to the department before you book contractors costs nothing and saves a stop-work order later.
For a condo or apartment, MPAJ will not process Borang 1A without the developer, JMB or MC’s consent, so the management office is effectively the first approval. Most buildings also set their own renovation deposit, working hours and lift-booking rules, and some restrict grille designs or awning colours on the facade. Read the building’s house rules before you finalise the design, then apply to MPAJ.
Borang 1A’s bill has a line for a fine, which is what MPAJ charges where work has started without approval. For bigger unapproved works the consequences go further; the renovating without a permit guide explains stop-work orders, demolition notices and regularising work after the fact.
| Area | What the page adds |
|---|---|
| Pandan Indah | Borang 1A and the materials permit in practice |
| Ampang house renovation | Costs across Ampang’s housing types |
| Ampang bathroom renovation | Bathroom costs and the DBKL / MPAJ split |
Borang 1A is the owner’s or tenant’s application, and landed additions are filed by the architect or plan drawer. ClickBina is an experienced KL & Selangor contractor: we do the renovation work and coordinate the trades, and we keep the scope inside the Borang 1A list where that is the route. WhatsApp us your area, property type and the work you have in mind; we reply within the hour, and the price we agree is a flat price with no hidden charges.