A renovation permit from DBKL (Dewan Bandaraya Kuala Lumpur) for small works is the minor-works permit (Permit Kerja Kecil): the building owner applies at the DBKL One Stop Centre or online through OSC 3.0 Plus, pays RM100 per permit, and each permit covers one item of work, which must be finished within three months. Work is allowed Monday to Saturday, 9am to 6pm. Re-tiling, plaster ceilings, welded grilles, a new gate or fence, a bigger water tank and repairs to existing plumbing all need a permit; painting, aircon, wiring, wallpaper, built-in cabinets and factory-made grilles do not. Condos and other residential strata apply through their JMB or MC, not straight to DBKL. These rules come from DBKL’s third-edition guideline, updated 30 September 2025.
DBKL’s Building Control Department (Jabatan Kawalan Bangunan) publishes a guideline that defines “minor works” and lets an owner apply without appointing a principal submitting person (PSP). It applies only to existing buildings in Kuala Lumpur that already hold a CF or CCC, and only to work inside the owner’s own premises or lot, never common property.
If your job falls outside these limits it is a building-plan submission, not a minor-works permit. The general rules for every council are in ClickBina’s renovation permit guide; this page covers DBKL only.
The 2025 guideline lists 17 kinds of work that need a minor-works permit. Grouped by where they happen:
| Area | Works on DBKL’s permit list | Limits written into the list |
|---|---|---|
| Gate and fence | Replacing an existing gate; replacing a fence with a masonry or other wall; installing a chain-link fence | Gate opening up to 6,100mm, no extra gate, homes only; wall up to 2.7m (1.8m solid plus 0.9m open), or 1.5m for terrace and linked houses |
| Outside the house | Replacing or repairing the perimeter drain in the lot; altering refuse-chamber piers; replacing render, ground-level floor finishes, external wall tiles or cladding | Inside your lot or boundary; refuse-chamber work for homes only |
| Inside the house | Replacing render and floor or wall finishes; installing or replacing a plaster ceiling; demolishing internal partitions back to the original layout | Partition work returns the layout to the original only |
| Openings and roof | Replacing existing windows, doors or roller shutters; repairing or replacing roof tiles | No new doors or windows; roof trusses not touched |
| Services | Replacing a water tank with a bigger one, more tanks or a new position; repairing existing piping and sanitary systems | No new support structure for the tank |
| Energy | EV charging bay; solar panels | Homes that are not strata-owned |
| Walls and grilles | Grilles welded in place on site; repairing or maintaining an existing party wall | Party-wall work needs the neighbour’s consent |
A second list in the same guideline names work that needs no permit, conditions or procedure at all:
No fee is charged for these. If you want something on file for a future sale or dispute, DBKL will issue a notification letter for record purposes on request.
Older articles, and some contractors, still quote the 2021 edition. The third edition changes several points that affect how you plan a job:
| Point | 2021 edition | 2025 third edition |
|---|---|---|
| Fee | A lower fee per permit | RM100 per permit, and RM100 for an extension |
| Works per permit | Several works on one permit | One minor work per permit |
| Working hours | 7am to 7pm | Monday to Saturday, 9am to 6pm; none on Sundays or public holidays |
| Solar panels, plumbing repairs, party walls | On the no-permit list | On the permit list |
| New permit items | — | EV charging bays and solar panels (non-strata homes), chain-link fences, removing partitions back to the original layout |
| Residential strata, including landed strata | — | Applies through the JMB or MC; the direct DBKL route is for commercial strata |
WhatsApp us your job details for a quote — we reply within the hour. A site visit is free. We serve KL, Selangor & Putrajaya.
💬 WhatsApp for a quoteThe “one work per permit” rule matters most. A job that re-tiles the kitchen, replaces the gate and adds a plaster ceiling is three permits, three fees and three three-month windows, so plan the sequence before the first application goes in.
Only the building owner may apply. The guideline gives two channels: the DBKL One Stop Centre (Pusat Setempat OSC) counter, or OSC 3.0 PLUS ONLINE DBKL, where the form is called “Permohonan Permit Sementara / Permit Kerja Kecil (B2-PK)”.
The minor-works guideline itself does not publish a processing time. DBKL’s 2025 customer-charter report lists minor-works (PK) permits under by-law 17 among the written permissions it aims to issue within 7 working days of full compliance, meaning once every document is in order. Treat that as the council’s target, not a promise for your file, and do not start work until the permit is in hand.
Once issued, the permit gives you three months to finish. If the work runs over, apply for an extension at the Building Control Department; if you want to add new work that the permit does not cover, that is a fresh application at the OSC.
For residential strata, including landed strata, the application goes through the JMB or MC rather than straight to DBKL; the direct DBKL route on the form is for commercial strata. Two further DBKL documents shape what a strata owner can do:
For what management offices usually ask for, see the KL condo renovation guide; for merging rooms rather than splitting them, see combining two bedrooms.
Extensions, extra storeys, a new entrance, structural changes and change of use all sit outside the minor-works route and need building plans submitted by a PSP (an architect or registered draughtsman, depending on the job). For terraces, DBKL also has separate renovation guidelines that depend on lot size; the Taman Tun area page and the Sri Petaling area page walk through the standard- and small-lot versions. Starting without approval carries real penalties, set out in the renovating without a permit guide.
These ClickBina pages apply the DBKL rules to particular neighbourhoods and their housing stock:
| Area | What the page adds |
|---|---|
| Sentul | Shoplots and older terraces, debris on busy roads, roof tanks |
| Setapak | Rental units and the no-permit list in practice |
| Cheras | The KL side of Cheras and the B2-PK form |
| Brickfields | Minor works on shophouses |
| Bangsar South | Condo parcels and the management body |
| Damansara (KL) | Bungalows and semi-detached houses |
| Kuala Lumpur house renovation | Costs and planning across the city |
Under DBKL’s guideline the permit is the owner’s application, so you, the owner, apply and sign the undertaking. ClickBina is an experienced KL & Selangor contractor: we do the renovation work and coordinate the trades, and we plan the work around DBKL’s hours, hoarding and debris rules so each three-month window is used well. WhatsApp us your area, property type and the work you have in mind; we reply within the hour, and the price we agree is a flat price with no hidden charges.