Renovation Permit MPS (Selayang, Rawang): Rules & Timing
🏠 Renovation🏢 Office Fit-Out🛍 Shop Fit-Out💦 Waterproofing❄ Aircon⚡ Electrical & Plumbing🔨 Carpentry🧹 Deep CleaningGuidesDesign IdeasToolsAbout🔍 SearchFree Quote
📋 Permits & Rules

Renovation Permit MPS (Selayang, Rawang, Batu Caves)
What Needs Approval, How to Apply, Fees & Timing

Tiles, grilles, wiring, ceilings, roof repairs and small awnings: the MPS minor-works permit and where it stops.

📍 We serve KL, Selangor & Putrajaya.

Selayang terrace house with a narrow post-free awning and new grilles being fitted

A renovation permit from MPS (Majlis Perbandaran Selayang) for small works is the minor-works permit (Permit Kerja-Kerja Kecil), applied for by the owner on checklist JB-B08 for landed homes or JB-B09 for strata homes. It covers repairing or changing doors and windows, tiling, iron grilles, electrical wiring that does not break walls, plaster ceilings, roof repairs that leave the structure alone, changes to an existing fence or wall, and awnings up to 4ft wide without posts. MPS charges a processing fee plus a sticker fee, both printed on the checklist. A new fence or wall (up to 1.8m), new structures, breaking walls or adding floor area need building plans through a PSP. The checklists do not give a processing time.

Who MPS covers and which form to use

MPS, whose portal still uses the name Majlis Perbandaran Selayang, covers Selayang, Batu Caves, Rawang and the Selangor side of Gombak. Its Building Department (Jabatan Bangunan) at Menara MPS in Bandar Baru Selayang handles renovation permits with two checklists that share the same works list:

ChecklistForExtra documents
JB-B08 (non-strata)Landed houses on individual titleNeighbour confirmation section on the form
JB-B09 (strata)Apartments, condominiums and other strata homesConsent or no-objection letter from the MC, developer or JMB, or their house rules; neighbour or MC/JMB confirmation

The council named on your assessment bill decides which forms apply; the Kuala Lumpur side of Gombak and Kepong is DBKL. ClickBina’s renovation permit guide covers the rules every council shares.

Works on the MPS minor-works list

The owner ticks the works on the application letter (Lampiran 1). The list is the same on both checklists:

  • Repairing or changing the type of doors and windows.
  • Laying tiles.
  • Fitting iron grilles.
  • Electrical wiring that does not involve breaking walls.
  • Plaster ceilings.
  • Repairing the roof without changing the original structure.
  • Altering an existing fence or wall.
  • Fitting an awning, up to 4ft wide and without posts.
  • Other works, described on the form.

Two items stand out against neighbouring councils. Wiring is a permit item at MPS, whereas DBKL lists small wiring jobs as needing no permit; and tiling and plaster ceilings are listed, so even a straightforward interior refresh goes through the counter. MPS does not publish a separate list of work that needs no permit.

Because the application letter lets you tick several items at once, a typical refresh of an older Selayang or Rawang terrace, say new tiles downstairs, a plaster ceiling, grilles on the windows and rewiring without hacking walls, can be described in one application rather than several. Describe each item as it will actually be done and mark it in red on the floor plan; vague descriptions are what lead to questions at the counter or a mismatch with what inspectors later see on site. If any item will need walls broken, for example to run new conduit, take it out of the minor-works application and ask about the building-plan route for that part.

Awnings, fences and where the permit stops

  • Awnings: only inside the owner’s lot, a maximum of 4ft wide and without posts. An awning that involves the neighbour or the boundary must have a gutter.
  • Existing fence or wall: altering it is on the minor-works list.
  • New fence or wall: submitted by a PSP with a detailed fence drawing, with a maximum height of 1.8m.
  • Bigger works: new structures or additions, breaking walls, or added floor area need building-plan approval through a qualified PSP.

Awnings are the job most often built wider than allowed. If you want more cover than a post-free 4ft awning gives, plan it as a building-plan job from the start; the awning design guide explains the options and materials.

Documents MPS asks for

  1. The owner’s application letter (Lampiran 1), naming the parts to be repaired.
  2. A copy of the title or sale and purchase agreement, complete with the building plan.
  3. A copy of the applicant’s IC, front and back on one clear sheet.
  4. A floor plan with the new works coloured red; for awnings, a sketch, sample image or specification catalogue; for a new fence or wall, a sketch of it.
  5. The latest paid assessment bill.
  6. A copy of the certificate of fitness or CCC (Form F) with the address list.
  7. Current colour images of the building, including the area to be worked on.
  8. For strata (JB-B09): the MC, developer or JMB’s consent or no-objection letter, or their house rules, a plan stamped by them if needed, and the neighbour’s consent or the MC or JMB’s confirmation.

Fees

Both checklists list two charges, paid at the counter: a processing fee and a sticker fee. The amounts are printed on the checklist; check the current form when you apply, because the versions on the MPS site are dated November 2019. The checklists do not list material-placement, bin or deposit charges for minor works, so ask the counter whether any apply to your job, especially if a lorry or bin will stand on the road.

Building-plan routes for additions and new fences carry their own fees, worked out by the PSP with the council.

Neighbours and responsibility

The forms make the applicant answerable for the neighbours. On the non-strata form, adjoining neighbours can sign to say they understand the roof or wall repair and whether they object, and the applicant promises to take full responsibility for any damage or complaints the works cause. On the strata form, the neighbour’s consent or the MC or JMB’s confirmation is part of the application.

A quiet word with the neighbours before you submit, and a look at shared walls and roof joints together, makes both the signature and the job easier. The party wall guide covers what happens when shared walls are damaged.

How to apply and how long it takes

  1. Confirm from your assessment bill that the property is under MPS.
  2. Choose JB-B08 or JB-B09, tick the works and gather the documents.
  3. Submit at the Building Department, Menara MPS, Persiaran 3, Bandar Baru Selayang, and pay the processing and sticker fees.
  4. The counter checks the file; the application is then approved, rejected or deferred by the department.
  5. Display the sticker and keep the work within what was approved.

The checklists do not state a processing time or permitted working hours. The Selayang area page sets out what the MPS customer charter says about building applications; for minor works, ask at the counter when you submit.

Apartments and condominiums

Strata owners use JB-B09. The management body comes first: MPS asks for its consent or no-objection letter, or its house rules, and any conditions it sets must be met before you apply. MPS’s Commissioner of Buildings department registers JMBs and MCs in its area, so management disputes go there rather than to the Building Department.

MPS area guides

AreaWhat the page adds
Debris and RORO binsBins and construction waste in practice
RawangAdditions and single houses on individual lots
GombakThe MPS and DBKL split, revaluation and strata

How ClickBina fits in

The MPS minor-works permit is the owner’s application, and building plans go through a PSP. ClickBina is an experienced KL & Selangor contractor: we do the renovation work and coordinate the trades, and we scope the job to what the MPS list allows, such as awning widths, so the approval matches what is built. WhatsApp us your area, property type and the work you have in mind; we'll reply as soon as we can, and the price we agree is a flat price with no hidden charges.

Sources & official references

Ready to get it sorted?

WhatsApp us your job details for a quote — we'll reply as soon as we can. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply on WhatsAppFlat price, no hidden chargesExperienced KL & Selangor contractor

Common Questions

Do I need an MPS permit to change tiles?
Yes. Laying tiles is on the MPS minor-works list, on both the landed (JB-B08) and strata (JB-B09) checklists.
Does rewiring need a permit in Selayang?
Electrical wiring that does not involve breaking walls is a minor-works item at MPS. Wiring that breaks walls or goes with structural change needs more.
How big can an awning be under the MPS minor-works permit?
Up to 4ft wide, without posts and inside your own lot. If it touches the neighbour or the boundary it needs a gutter.
Can I build a new fence with an MPS minor-works permit?
No. A new fence or wall is submitted by a PSP with a detailed drawing, up to 1.8m high. Altering an existing fence is a minor work.
How long does MPS take to approve a minor-works permit?
The checklists do not give a processing time. Ask at the Building Department counter when you submit.
What does a condo owner in Selayang need for an MPS permit?
Checklist JB-B09 plus the MC, developer or JMB’s consent or no-objection letter, or their house rules, and the neighbour’s consent or the management’s confirmation.
Is it MPS or MBSel?
The council’s own portal still uses Majlis Perbandaran Selayang (MPS), and its forms carry that name.
How do I apply for an MPS renovation permit?
Confirm from your assessment bill that the property is under MPS, then choose checklist JB-B08 (landed) or JB-B09 (strata), tick the works on the application letter and gather the documents. Submit at the Building Department, Menara MPS, Bandar Baru Selayang, and pay the processing and sticker fees. Once approved, display the sticker and keep the work within what was approved.
Can I check or apply for an MPS permit online?
The JB-B08 and JB-B09 checklists can be downloaded from the MPS website, and the process they set out is submission at the Building Department counter. The checklists do not mention an online submission or status check, so ask the counter how to follow up your application when you submit.
Do house repairs need an MPS permit?
Many do. Repairing or changing doors and windows, and repairing the roof without changing its structure, are on the MPS minor-works list, alongside tiling, grilles, plaster ceilings and wiring that does not break walls. Work that breaks walls, adds floor area or changes the structure needs building plans through a PSP.