Renovation Permit MPKj (Kajang): Rules, Fees & Timing
🏠 Renovation🏢 Office Fit-Out🛍 Shop Fit-Out💦 Waterproofing❄ Aircon⚡ Electrical & Plumbing🔨 Carpentry🧹 Deep CleaningGuidesDesign IdeasToolsAbout🔍 SearchFree Quote
📋 Permits & Rules

Renovation Permit MPKj (Kajang, Bangi, Semenyih)
What Needs Approval, How to Apply, Fees & Timing

Floor and roof finishes, grilles, doors, windows and awnings: MPKj’s minor-works permit and when a job needs more.

📍 We serve KL, Selangor & Putrajaya.

Kajang terrace house with a new awning and window grilles being fitted at the front

A renovation permit from MPKj (Majlis Perbandaran Kajang) for small works is the minor-works permit (Permit Bagi Kerja-Kerja Kecil), and it covers only three kinds of work: changing floor and roof finishes, fitting grilles or changing doors and windows, and installing an awning. The owner applies to MPKj’s Building Control Department with the council’s sketches; the form costs RM5, processing is RM120 per application, an awning plan is RM100 and the plan deposit RM200, and approval lasts one year. Extensions and other designs go through an architect or registered draughtsman. MPKj does not publish a processing time or working hours for these permits.

Which MPKj route your job needs

MPKj covers Kajang town, Bandar Baru Bangi, Semenyih, Balakong, Sungai Long and the Selangor side of Cheras. Its Building Control Department (Jabatan Kawalan Bangunan) has separate routes for different sizes of job:

RouteWhat it coversWho prepares it
Minor-works permit (form B10)Floor and roof finishes; grilles, doors and windows; awningsThe owner, using the council’s sketches
Pelan setara bookletStandard sketches for common terrace additions such as rear extensions and brick fencesThe owner, within the sketch dimensions
Residential extension planExtensions to terrace, semi-detached and detached housesA consultant (architect or registered draughtsman)
Plan amendment (pelan pelarasan)Changes to a plan MPKj has already approvedA consultant

This page focuses on the minor-works permit and points to ClickBina’s area pages for the other routes. The rules every council shares are in the renovation permit guide.

What the minor-works permit covers

The form, in use from 20 July 2022, lists three types of work:

  1. Changing floor and roof finishes. The owner prepares the sketch.
  2. Fitting grilles or changing doors and windows. The owner prepares the sketch.
  3. Installing an awning. Uses the council’s awning plan, charged per plan.

The sketches and specifications in MPKj’s booklet may not be changed in any way; an altered sketch means the application is rejected. An owner who wants a design other than the booklet’s must submit plans through an architect or registered draughtsman. Any structure must stay inside the owner’s own lot. Interior jobs outside these three types, such as kitchens, cabinets or plaster ceilings, are not on this form; MPKj does not publish a list of work that needs no permit, so ask the department about them.

Fees on the MPKj form

ChargeAmount
Minor-works application formRM5
Processing feeRM120 per application
Plan fee (awning)RM100 per plan
Plan depositRM200
Permit to place building materialsRM100 a month
Permit to place a RORO binRM100 a month
Petil (file) chargeA small fixed charge on the bill

Want this priced for your home?

WhatsApp us your job details for a quote — we reply within the hour. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

The deposit is returned under the terms of the owner’s deposit undertaking. If the work departs from the approved plan, the owner accepts on the form that the deposit will not be returned.

Two practical points follow from the fee table. First, the monthly permits are the only charges that grow with time, so order materials close to the day they are needed and book the bin for the demolition days rather than for the whole job. Second, each application carries its own processing fee, so a project that changes the floor finish and adds an awning is worth planning as one submission with both sketches, rather than two separate visits to the counter. Confirm with the department how it wants multiple work types presented before you file.

Documents to prepare

  • The completed application form and one copy of the owner’s IC.
  • The latest paid assessment bill; if none has been issued yet, a letter from MPKj’s valuation department.
  • The certificate of fitness or Form F.
  • The sale and purchase agreement and the title (and the tenancy agreement if relevant).
  • Two copies of the floor plan for floor and roof finishes, grilles, doors or windows.
  • Dated site images of the front, back and sides, taken no more than seven days before the application is registered.
  • Earlier approval letters and plans, if any.
  • The depositor’s undertaking, signed before a Commissioner for Oaths and stamped, and the bin receipt if relevant.

How to apply

  1. Measure what is there: the building, the lot and the distances from the front, side and back boundaries.
  2. Choose the work type and complete the council’s sketch for it without changing it.
  3. Submit the form, sketches and documents to the Building Control Department, Majlis Perbandaran Kajang.
  4. Pay the bill, including the monthly materials or bin permits if anything will sit outside your lot.
  5. Start only once approval is issued, and keep the work within the sketch.

One-year approval, timing and hours

  • Validity: the approval is valid for one year only. To build after it expires, you make a new application and pay the fees again.
  • Processing time: not published on the form. Ask at the Building Control Department counter.
  • Working hours: not published on the form. Check with MPKj, and with your management office in a strata development.

A one-year window is generous for finishes and grilles, but it runs from approval, not from the day work starts. If the job depends on a long lead time, such as custom doors or an awning frame made to measure, order before you apply or allow for the wait, so the approval does not lapse halfway through.

If the work does not match the approved sketch

MPKj’s form puts the risk on the owner. The owner is fully responsible for the stability and strength of everything built, MPKj accepts no liability for design or structural failure, and the owner undertakes to answer complaints and repair any damage to neighbouring buildings. Under section 70(13)(b) of the Street, Drainage and Building Act 1974, building differently from an approved plan without written permission can, on conviction, bring a fine of up to RM50,000 plus RM1,000 for every day the offence continues. The renovating without a permit guide covers enforcement in more detail.

Extensions, standard plans and amendments

Anything that adds floor area goes beyond the minor-works permit. ClickBina’s area pages cover the other MPKj routes in detail: the Bandar Mahkota Cheras page walks through the pelan setara booklet and its sketches, the Semenyih page explains the residential extension guideline and its deposit scale, and the Bangi page covers amending an approved plan and opening party walls.

Condos and apartments

The minor-works form is written around landed houses and does not set out a separate strata route. In a condo or apartment, start with the JMB or MC’s renovation rules and ask MPKj whether your job needs the council as well. Inter-floor leaks are a different process, handled through MPKj’s Commissioner of Buildings; the Balakong page explains it.

MPKj area guides

AreaWhat the page adds
KajangThe council area, extensions through a consultant, enforcement
Sungai LongDetached houses, pools and retaining walls
Kajang house renovationCosts and housing generations
Bangi house renovationCosts for Bangi’s terraces

How ClickBina fits in

The minor-works permit is the owner’s application, made with the council’s sketches. ClickBina is an experienced KL & Selangor contractor: we do the renovation work and coordinate the trades, keep the job inside the approved sketch, and plan deliveries so the monthly materials and bin permits run as short as possible. WhatsApp us your area, house type and the work you have in mind; we reply within the hour, and the price we agree is a flat price with no hidden charges.

Sources & official references

Ready to get it sorted?

WhatsApp us your job details for a quote — we reply within the hour. A site visit is free. We serve KL, Selangor & Putrajaya.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

Common Questions

What does the MPKj minor-works permit cover?
Three kinds of work: changing floor and roof finishes, fitting grilles or changing doors and windows, and installing an awning.
How much is an MPKj renovation permit?
RM5 for the form, RM120 processing per application, RM100 per awning plan and a RM200 plan deposit, plus RM100 a month each for materials or a RORO bin placed outside.
How long is MPKj approval valid?
One year. After that you apply again and pay the fees again.
Can I draw my own plan for MPKj?
For floor and roof finishes, grilles, doors and windows, the owner prepares the sketch on MPKj’s template. Any other design goes through an architect or registered draughtsman.
How long does MPKj take to approve a minor-works permit?
MPKj does not publish a processing time on the form. Ask at the Building Control Department when you submit.
What happens if I build differently from the approved MPKj sketch?
You can lose the deposit, and on conviction face a fine of up to RM50,000 plus RM1,000 for each day the offence continues.
Do I need an MPKj permit for a kitchen renovation?
Kitchen work is not one of the three types on the minor-works form, and MPKj publishes no exempt list. Ask the department, and your JMB or MC if you live in a strata development.