New Terrace House Renovation
What to Do First After VP

Just got the keys? A new house is renovated in a different order from an old one. Here is how to protect your DLP claim and avoid paying twice.

Newly completed double-storey terrace house with a bare developer finish and short car porch

In a brand-new terrace house, check and report the developer's defects first, then renovate in a planned order: security and services before finishes, and any extension only with council approval. The defect liability period runs 24 months from vacant possession, and it does not cover improvements or additions you make after handover, so work that disturbs a defect can cost you the claim. ClickBina's terrace renovation guide puts a light refresh at RM30,000 – RM55,000 and a full rear extension runs RM40,000 – RM120,000 (indicative 2026, Klang Valley).

Why a new house is renovated differently

An old terrace is renovated to fix what has worn out. A new one is renovated to finish what the developer left basic: the kitchen has no cabinets or only a slab, the yard is open, there is no grille, the lighting is a bare point per room, and the car porch may stop short. At the same time, the house is still inside the developer's defect liability period, so the order of work matters more than in any other renovation.

The owners who get this right follow three rules: defects before renovation, services before finishes, and approval before any extension.

Step one: defects before renovation

ClickBina's defect liability period guide explains the rule: the DLP is 24 months from the date of vacant possession for houses bought from a housing developer. It also lists what is not covered, including damage caused by the buyer, unauthorised renovations and improvements or additions made by the buyer after handover.

So before any contractor starts, inspect the house properly, list every defect in writing with the date, submit it to the developer and give them the chance to repair. Leaks, hollow tiles, cracks, doors that do not close and poor falls to floor traps are all easier to claim while nothing has been changed. If a renovation hacks the tiles over a leaking bathroom, it becomes much harder to show whose fault the leak is.

⚠️ Tiles, waterproofing and plumbing in bathrooms are the most common source of disputes. Get any wet-area defects repaired and water-tested by the developer before you retile or add a shower screen.

Check the rules before you design

Three sets of rules shape a new-house renovation:

  • The council: structural work, extensions, new roofs and car porch extensions need approval; our renovation permit guide explains which works need what.
  • The developer or township: some new townships issue renovation guidelines covering the front facade, fences, roof colour and working hours. Ask the developer or the residents' association before you design.
  • Gated and guarded communities: the management may set contractor registration, work hours, deposits and rules for bringing in lorries and bins.

Building an extension without approval has real consequences. The illegal extension guide explains what councils can do, including ordering an unauthorised structure to be demolished.

What new terrace owners usually do first

WorkWhy it comes earlyWhat to watch
Security: grilles, autogate, CCTVThe house is empty and the area is still being builtGrille design that does not block a fire escape
Kitchen cabinets and wet kitchenThe developer kitchen is usually basicWater and gas points, hood ducting, drainage
Wardrobes and built-insStorage is needed before moving inLeave space for aircon and sockets
Aircon points and wiringChasing walls later damages new finishesCircuit capacity, pipe routes, outdoor unit positions
Plaster ceiling and lightingWiring and ceiling go in togetherAccess for maintenance above the ceiling
Car porch or rear extensionAdds usable spaceCouncil approval, setbacks, drain line

The right order of work

  1. Inspect, report defects and let the developer repair them.
  2. Decide the full plan, even if you build it in stages, so later work does not undo earlier work.
  3. Apply for any approvals: extension, car porch, structural changes.
  4. Structure and roof: extension, porch, any hacking.
  5. Services: electrical, aircon piping, plumbing, water filter points.
  6. Ceiling and lighting, then tiling and waterproofing in any new wet areas.
  7. Carpentry: kitchen, wardrobes and built-ins.
  8. Painting, cleaning, then move in.

Carpentry and paint last is the rule most often broken. A kitchen fitted before the aircon piping and ceiling wiring are done usually gets scratched or has to be removed for access.

Extending the house: rear, side and car porch

Most new terraces are extended at the back first, to enclose the yard as a wet kitchen, or at the front, to extend the car porch roof. Our rear kitchen extension guide explains the open-space rules behind the house, building next to the drain and the approval route. For the porch, the pelan setara guide covers the simplified approval some councils offer for car porch works.

Corner and end lots have side land and more options, but also setbacks. Whatever you extend, get the drawings approved before the builder starts, not after.

What a first renovation costs

These are ClickBina's published ranges (indicative 2026, Klang Valley). A new house usually needs less repair than an old one, so the money goes into kitchen, storage, security and extension.

ItemIndicative priceSource guide
Light refresh: paint, kitchen cabinets, minor repairs, lightingRM30,000 – RM55,000Terrace renovation guide
Kitchen renovation (cabinets, hob, hood)RM15,000 – RM45,000Terrace renovation guide
Built-in wardrobes, per roomRM3,500 – RM9,000Terrace renovation guide
Plaster ceiling, per roomRM1,200 – RM3,500Terrace renovation guide
Basic rear roomRM18,000 – RM50,000Rear kitchen extension guide
Full rear extension (tiling, electrical, plumbing)RM40,000 – RM120,000Rear kitchen extension guide
Mid-range enclosed wet kitchenRM25,000 – RM40,000Rear kitchen extension guide
Plans by an architect or draughtsmanRM3,000 – RM10,000Rear kitchen extension guide

Want this priced for your home?

WhatsApp us your job details for a quote — we reply within the hour.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

The terrace house renovation guide has the full scope tiers and a worked example if you plan a larger job.

Doing it in stages without paying twice

Many new owners cannot do everything at once. That is fine, as long as the first stage leaves room for the second. Run spare conduits and aircon piping routes before the ceiling closes, put water and drain points where a future wet kitchen will go, and choose floor tiles you can still buy later. A staged plan that is drawn once costs far less than three separate renovations that each undo part of the last.

Common mistakes in new-house renovations

  • Renovating over a defect before the developer has repaired it.
  • Extending without approval because neighbours have done the same.
  • Fitting the kitchen and wardrobes before the wiring, aircon and ceiling are finished.
  • Hacking the developer's tiles only to find the waterproofing underneath was the real problem.
  • Forgetting to leave access to stop valves, the DB box and the ceiling space.

How ClickBina can help

ClickBina is an experienced KL & Selangor contractor for whole-house refurbishment and trade coordination, so a new-house renovation can be planned and sequenced as one job rather than a string of separate trades. WhatsApp us your job details for a quote: the location, the layout, your key collection date and what you want done first. We reply within the hour, the price we agree is a flat price with no hidden charges, and a site visit is RM150, waived if you go ahead.

Sources & methodology

  • ClickBina defect liability period guide — the 24-month DLP from vacant possession and what it does not cover.
  • ClickBina terrace house renovation guide — scope tiers and work-type prices.
  • ClickBina rear kitchen extension guide — extension, wet kitchen and plan prices.

How we estimated prices: every RM figure on this page is quoted unchanged from the ClickBina guides named above; they are indicative Klang Valley ranges for 2026, not a quote for your house.

Ready to get it sorted?

WhatsApp us your job details for a quote — we reply within the hour.

💬 WhatsApp for a quote
Reply within the hourFlat price, no hidden chargesExperienced KL & Selangor contractor

Common Questions

Should I renovate before or after reporting defects to the developer?
After. Report defects in writing and let the developer repair them first; the DLP does not cover improvements or additions you make after handover.
How long is the defect liability period for a new house?
ClickBina's DLP guide puts it at 24 months from the date of vacant possession for houses bought from a housing developer.
Do I need approval to extend my new terrace house?
Yes, extensions and car porch roofs need council approval; some councils offer a simplified pelan setara route for car porch works.
What should I do first in a new terrace house?
Usually security, the kitchen, wardrobes, aircon points and lighting, with any extension approved before it is built.
How much does a first renovation cost?
ClickBina's terrace guide puts a light refresh at RM30,000–RM55,000 and a kitchen renovation at RM15,000–RM45,000 (indicative 2026, Klang Valley).
How much is a rear extension?
ClickBina's rear kitchen extension guide puts a basic rear room at RM18,000–RM50,000 and a full rear extension at RM40,000–RM120,000.
Can I renovate in stages?
Yes, if the whole plan is drawn first so conduits, piping and water points for later stages go in early.