Just got the keys? A new house is renovated in a different order from an old one. Here is how to protect your DLP claim and avoid paying twice.

In a brand-new terrace house, check and report the developer's defects first, then renovate in a planned order: security and services before finishes, and any extension only with council approval. The defect liability period runs 24 months from vacant possession, and it does not cover improvements or additions you make after handover, so work that disturbs a defect can cost you the claim. ClickBina's terrace renovation guide puts a light refresh at RM30,000 – RM55,000 and a full rear extension runs RM40,000 – RM120,000 (indicative 2026, Klang Valley).
An old terrace is renovated to fix what has worn out. A new one is renovated to finish what the developer left basic: the kitchen has no cabinets or only a slab, the yard is open, there is no grille, the lighting is a bare point per room, and the car porch may stop short. At the same time, the house is still inside the developer's defect liability period, so the order of work matters more than in any other renovation.
The owners who get this right follow three rules: defects before renovation, services before finishes, and approval before any extension.
ClickBina's defect liability period guide explains the rule: the DLP is 24 months from the date of vacant possession for houses bought from a housing developer. It also lists what is not covered, including damage caused by the buyer, unauthorised renovations and improvements or additions made by the buyer after handover.
So before any contractor starts, inspect the house properly, list every defect in writing with the date, submit it to the developer and give them the chance to repair. Leaks, hollow tiles, cracks, doors that do not close and poor falls to floor traps are all easier to claim while nothing has been changed. If a renovation hacks the tiles over a leaking bathroom, it becomes much harder to show whose fault the leak is.
Three sets of rules shape a new-house renovation:
Building an extension without approval has real consequences. The illegal extension guide explains what councils can do, including ordering an unauthorised structure to be demolished.
| Work | Why it comes early | What to watch |
|---|---|---|
| Security: grilles, autogate, CCTV | The house is empty and the area is still being built | Grille design that does not block a fire escape |
| Kitchen cabinets and wet kitchen | The developer kitchen is usually basic | Water and gas points, hood ducting, drainage |
| Wardrobes and built-ins | Storage is needed before moving in | Leave space for aircon and sockets |
| Aircon points and wiring | Chasing walls later damages new finishes | Circuit capacity, pipe routes, outdoor unit positions |
| Plaster ceiling and lighting | Wiring and ceiling go in together | Access for maintenance above the ceiling |
| Car porch or rear extension | Adds usable space | Council approval, setbacks, drain line |
Carpentry and paint last is the rule most often broken. A kitchen fitted before the aircon piping and ceiling wiring are done usually gets scratched or has to be removed for access.
Most new terraces are extended at the back first, to enclose the yard as a wet kitchen, or at the front, to extend the car porch roof. Our rear kitchen extension guide explains the open-space rules behind the house, building next to the drain and the approval route. For the porch, the pelan setara guide covers the simplified approval some councils offer for car porch works.
Corner and end lots have side land and more options, but also setbacks. Whatever you extend, get the drawings approved before the builder starts, not after.
These are ClickBina's published ranges (indicative 2026, Klang Valley). A new house usually needs less repair than an old one, so the money goes into kitchen, storage, security and extension.
| Item | Indicative price | Source guide |
|---|---|---|
| Light refresh: paint, kitchen cabinets, minor repairs, lighting | RM30,000 – RM55,000 | Terrace renovation guide |
| Kitchen renovation (cabinets, hob, hood) | RM15,000 – RM45,000 | Terrace renovation guide |
| Built-in wardrobes, per room | RM3,500 – RM9,000 | Terrace renovation guide |
| Plaster ceiling, per room | RM1,200 – RM3,500 | Terrace renovation guide |
| Basic rear room | RM18,000 – RM50,000 | Rear kitchen extension guide |
| Full rear extension (tiling, electrical, plumbing) | RM40,000 – RM120,000 | Rear kitchen extension guide |
| Mid-range enclosed wet kitchen | RM25,000 – RM40,000 | Rear kitchen extension guide |
| Plans by an architect or draughtsman | RM3,000 – RM10,000 | Rear kitchen extension guide |
WhatsApp us your job details for a quote — we reply within the hour.
💬 WhatsApp for a quoteThe terrace house renovation guide has the full scope tiers and a worked example if you plan a larger job.
Many new owners cannot do everything at once. That is fine, as long as the first stage leaves room for the second. Run spare conduits and aircon piping routes before the ceiling closes, put water and drain points where a future wet kitchen will go, and choose floor tiles you can still buy later. A staged plan that is drawn once costs far less than three separate renovations that each undo part of the last.
ClickBina is an experienced KL & Selangor contractor for whole-house refurbishment and trade coordination, so a new-house renovation can be planned and sequenced as one job rather than a string of separate trades. WhatsApp us your job details for a quote: the location, the layout, your key collection date and what you want done first. We reply within the hour, the price we agree is a flat price with no hidden charges, and a site visit is RM150, waived if you go ahead.
How we estimated prices: every RM figure on this page is quoted unchanged from the ClickBina guides named above; they are indicative Klang Valley ranges for 2026, not a quote for your house.